New webinars published monthly

NEC4 webinars

Running an NEC4 contract well requires more than knowing the clauses exist. You need to understand how early warnings connect to compensation events, how time bars can extinguish your entitlement overnight, and why your site records are the single most important commercial asset on any project.

Prefer to listen? Available as The NEC4 Brief on Spotify and Apple Podcasts

NEC4: How to approach Option Z / amendments

Learn when and how to draft Option Z additional conditions in NEC4 contracts. Practical guidance on avoiding common pitfalls and engaging your supply chain.

NEC4: Ep.05 - Programme: Getting it working for you

Expert analysis of NEC4 programme management covering acceptance consequences, compensation events, time risk allowance, and practical tips for project teams.

NEC4: Notifying compensation events and instructing quotations

NEC4 compensation event notification and quotation instruction explained. Expert guidance on Clause 61 and 62 procedures.

NEC4: Assessing compensation events part 2 - Price

Part 2 of our NEC4 CE assessment series. Master price assessment, defined cost calculations, and fee application under Option A-E contracts.

NEC4 - Taming Commercial Chaos | NEC People Conference 2025 London

Ben Walker's NEC People Conference 2025 presentation on taming commercial chaos through structured site records and AI-powered CE detection.

NEC4: Assessing Compensation Events Part 1 - Time

Part 1 of our NEC4 CE assessment series. Learn how to assess time impacts and prepare robust extension of time submissions.

Ben Walker: Decoding NEC Contracts and the Value of Site Records

Ben Walker decodes NEC contracts and explains why contemporaneous site records are essential for commercial success on infrastructure projects.

NEC Contract Early Warnings: A Positive Approach to Project Management

Understand NEC4 early warnings with expert Ben Walker. Learn proactive project management through proper Clause 15 implementation.
Ben Walker, Commercial Director at Gather

Ben Walker

Commercial Director, Gather

Ben was involved in the drafting of NEC4 contract clauses and previously founded CEMAR, the UK's most widely used NEC contract management system. He brings over 20 years of experience in construction commercial management and has delivered NEC4 training to contractors and clients across the UK and internationally, including the Falkland Islands. At Gather, Ben leads the development of the platform's NEC4-aligned record management capabilities.

Glenn Hide, Director at GMH Planning

Glenn Hide

Director, GMH Planning

Glenn is one of the UK's foremost NEC consultants and the author of the CECA NEC4 Bulletin series, which provides practical guidance on NEC4 contract administration to civil engineering contractors nationwide. He delivers NEC4 training workshops, produces free NEC guidance notes at gmhplanning.co.uk, and is a regular speaker at industry events including the NEC People Conference.

Frequently Asked Questions

What are compensation events in NEC4?

Compensation events are the mechanism within NEC4 contracts that allows the contractor to adjust prices, the Completion Date, or Key Dates when certain specified events occur that are not the contractor's fault. The standard NEC4 Engineering and Construction Contract (ECC) lists 21 compensation events under Clause 60.1. These include instructions that change the Scope, failure to provide site access, physical conditions the contractor could not have reasonably foreseen, and weather measurements exceeding defined thresholds. The contractor must notify most compensation events within eight weeks of becoming aware that the event has occurred, or they lose their entitlement to additional time and money.

What is the NEC4 eight-week time bar?

Under Clause 61.3 of the NEC4 ECC, if the contractor does not notify a compensation event within eight weeks of becoming aware that it has happened, the prices, Completion Date, and Key Dates are not changed. This time bar is strict and has been upheld consistently. However, it does not apply to compensation events that arise from the Project Manager or Supervisor giving an instruction, issuing a certificate, or changing an earlier decision. In practice, this means the time bar applies to events such as unforeseen physical conditions, weather, and access issues, but not to scope changes instructed by the Project Manager.

How do NEC4 early warnings work?

Under Clause 15.1 of the NEC4 ECC, both the Contractor and the Project Manager must give an early warning by notifying the other as soon as either becomes aware of any matter that could increase the total of the Prices, delay Completion, delay meeting a Key Date, or impair the performance of the works in use. Early warnings are recorded in the Early Warning Register, maintained by the Project Manager, and discussed at regular early warning meetings at intervals set in Contract Data Part One. Early warnings are not compensation events, but failure to give an early warning that an experienced contractor could have given may reduce the assessed value of a subsequent compensation event under Clause 63.7.

What records do you need under NEC4?

NEC4 contracts require robust contemporaneous records to support virtually every contractual process. At a minimum, contractors should maintain daily site diaries recording labour, plant, materials, weather conditions, progress achieved, instructions received, and any events that could affect time or cost. These records directly support early warning notifications, compensation event evidence, programme updates under Clause 32, payment applications, and defence against Disallowed Cost under Options C, D, E, and F. The quality of your records determines the quality of your commercial outcomes.

What is the dividing date in NEC4?

The dividing date is a key concept introduced in NEC4 for assessing compensation events. It separates actual work done from forecast work not yet done. For compensation events arising from Project Manager instructions, the dividing date is the date of the instruction. For other events, it is the date of the compensation event notification. The accepted programme current at the dividing date forms the baseline for assessment: actual costs before the dividing date are used as recorded, while costs after the dividing date are forecast. This prevents assessments from becoming moving targets as administrative delays occur.

What is Disallowed Cost under NEC4?

Disallowed Cost is a concept specific to NEC4 target cost and cost-reimbursable contracts (Options C, D, E, and F). It refers to costs that the client will not include in the assessment of the contractor's share, even if they were genuinely incurred. Grounds for Disallowed Cost include costs arising from the contractor not following a contractual requirement, not giving an early warning that an experienced contractor could have given, or costs that cannot be justified with records. Maintaining detailed, traceable records of all resources and their usage is the primary defence against Disallowed Cost.

Why Gather Hosts NEC4 Webinars

Gather was built by quantity surveyors and contract experts who spent years watching projects lose money not because the work was done badly, but because the records were incomplete, scattered, or arrived too late. Our platform captures site data in a structure that maps directly to NEC4 processes. These webinars exist because better contract knowledge leads to better project outcomes for everyone.

Over 2,750 construction professionals attended live sessions

Complete NEC4 Reference

The Contractor's Guide to NEC4

Ten deep-dive guides covering every clause that affects your bottom line. Written for commercial teams managing NEC4 contracts on live projects, with worked examples, common mistakes, and practical checklists.