NEC4 webinars
Running an NEC4 contract well requires more than knowing the clauses exist. You need to understand how early warnings connect to compensation events, how time bars can extinguish your entitlement overnight, and why your site records are the single most important commercial asset on any project.
Prefer to listen? Available as The NEC4 Brief on Spotify and Apple Podcasts
The NEC4 Lifecycle
What You Will Learn
This is not theoretical contract law. Every session is built around the practical challenges that project teams face every day on NEC4 projects across rail, highways, water, energy, and nuclear.
Early Warnings
Clause 15
How to use the early warning process as the risk management tool it was designed to be, not the box-ticking exercise it often becomes.
Compensation Events & Quotations
Clauses 60 & 61
The rules that determine whether you get paid for change. Who notifies what, the critical eight-week time bar, and why timelines are limits, not targets.
Assessing CEs: Time
Clauses 62 & 63
How to assess time impact using the accepted programme, the dividing date, and prospective delay analysis. Why NEC4 does not permit global delay claims.
Assessing CEs: Price
Defined Cost
How Defined Cost works under different main options, the Schedule of Cost Components, and what makes a quotation robust enough to accept.
The Value of Site Records
Commercial Assurance
Why contemporaneous records underpin every single NEC4 process, from early warnings to payment applications, and what happens when they are incomplete.
Taming Commercial Chaos
Culture, Knowledge, Discipline
How to shift from reactive contract administration to proactive project management using the three pillars of NEC success.

NEC4: How to approach Option Z / amendments

NEC4: Ep.05 - Programme: Getting it working for you

NEC4: Notifying compensation events and instructing quotations

NEC4: Assessing compensation events part 2 - Price

NEC4 - Taming Commercial Chaos | NEC People Conference 2025 London

NEC4: Assessing Compensation Events Part 1 - Time

Ben Walker: Decoding NEC Contracts and the Value of Site Records

NEC Contract Early Warnings: A Positive Approach to Project Management
Your Presenters
Ben Walker
Commercial Director, Gather
Ben was involved in the drafting of NEC4 contract clauses and previously founded CEMAR, the UK's most widely used NEC contract management system. He brings over 20 years of experience in construction commercial management and has delivered NEC4 training to contractors and clients across the UK and internationally, including the Falkland Islands. At Gather, Ben leads the development of the platform's NEC4-aligned record management capabilities.
Glenn Hide
Director, GMH Planning
Glenn is one of the UK's foremost NEC consultants and the author of the CECA NEC4 Bulletin series, which provides practical guidance on NEC4 contract administration to civil engineering contractors nationwide. He delivers NEC4 training workshops, produces free NEC guidance notes at gmhplanning.co.uk, and is a regular speaker at industry events including the NEC People Conference.
NEC4 Explained
Frequently Asked Questions
What are compensation events in NEC4?
Compensation events are the mechanism within NEC4 contracts that allows the contractor to adjust prices, the Completion Date, or Key Dates when certain specified events occur that are not the contractor's fault. The standard NEC4 Engineering and Construction Contract (ECC) lists 21 compensation events under Clause 60.1. These include instructions that change the Scope, failure to provide site access, physical conditions the contractor could not have reasonably foreseen, and weather measurements exceeding defined thresholds. The contractor must notify most compensation events within eight weeks of becoming aware that the event has occurred, or they lose their entitlement to additional time and money.
What is the NEC4 eight-week time bar?
Under Clause 61.3 of the NEC4 ECC, if the contractor does not notify a compensation event within eight weeks of becoming aware that it has happened, the prices, Completion Date, and Key Dates are not changed. This time bar is strict and has been upheld consistently. However, it does not apply to compensation events that arise from the Project Manager or Supervisor giving an instruction, issuing a certificate, or changing an earlier decision. In practice, this means the time bar applies to events such as unforeseen physical conditions, weather, and access issues, but not to scope changes instructed by the Project Manager.
How do NEC4 early warnings work?
Under Clause 15.1 of the NEC4 ECC, both the Contractor and the Project Manager must give an early warning by notifying the other as soon as either becomes aware of any matter that could increase the total of the Prices, delay Completion, delay meeting a Key Date, or impair the performance of the works in use. Early warnings are recorded in the Early Warning Register, maintained by the Project Manager, and discussed at regular early warning meetings at intervals set in Contract Data Part One. Early warnings are not compensation events, but failure to give an early warning that an experienced contractor could have given may reduce the assessed value of a subsequent compensation event under Clause 63.7.
What records do you need under NEC4?
NEC4 contracts require robust contemporaneous records to support virtually every contractual process. At a minimum, contractors should maintain daily site diaries recording labour, plant, materials, weather conditions, progress achieved, instructions received, and any events that could affect time or cost. These records directly support early warning notifications, compensation event evidence, programme updates under Clause 32, payment applications, and defence against Disallowed Cost under Options C, D, E, and F. The quality of your records determines the quality of your commercial outcomes.
What is the dividing date in NEC4?
The dividing date is a key concept introduced in NEC4 for assessing compensation events. It separates actual work done from forecast work not yet done. For compensation events arising from Project Manager instructions, the dividing date is the date of the instruction. For other events, it is the date of the compensation event notification. The accepted programme current at the dividing date forms the baseline for assessment: actual costs before the dividing date are used as recorded, while costs after the dividing date are forecast. This prevents assessments from becoming moving targets as administrative delays occur.
What is Disallowed Cost under NEC4?
Disallowed Cost is a concept specific to NEC4 target cost and cost-reimbursable contracts (Options C, D, E, and F). It refers to costs that the client will not include in the assessment of the contractor's share, even if they were genuinely incurred. Grounds for Disallowed Cost include costs arising from the contractor not following a contractual requirement, not giving an early warning that an experienced contractor could have given, or costs that cannot be justified with records. Maintaining detailed, traceable records of all resources and their usage is the primary defence against Disallowed Cost.
Why Gather
Why Gather Hosts NEC4 Webinars
Gather was built by quantity surveyors and contract experts who spent years watching projects lose money not because the work was done badly, but because the records were incomplete, scattered, or arrived too late. Our platform captures site data in a structure that maps directly to NEC4 processes. These webinars exist because better contract knowledge leads to better project outcomes for everyone.
Over 2,750 construction professionals attended live sessions
Complete NEC4 Reference
The Contractor's Guide to NEC4
Ten deep-dive guides covering every clause that affects your bottom line. Written for commercial teams managing NEC4 contracts on live projects, with worked examples, common mistakes, and practical checklists.
Early Warnings
Clause 15
How to use the early warning register as a risk management tool. The clause 63.7 sanction that reduces your CE recovery when you forget.
Read guideCompensation Events
Clauses 60–65
All 21 clause 60.1 categories, the notification process, deeming provisions, and a worked example from identification to implementation.
Read guideEight-Week Time Bar
Clause 61.3
The absolute deadline for notifying compensation events. How it works, when the clock starts, and the only exceptions in the contract.
Read guideWeather Delays
Clause 60.1(13)
How the one-in-ten-year weather test works, what measurements to compare against Contract Data, and the mistakes that lose entitlement.
Read guideDividing Date
Clause 63.6
The line that separates actual cost from forecast in every CE assessment. How it works and why getting it wrong changes the numbers.
Read guideDisallowed Cost
Clause 11.2(26)
The eleven categories of cost the Project Manager can deduct. How to avoid disallowance and how to challenge it when it happens.
Read guidePayment
Clauses 50–53
The payment cycle from assessment date to certified amount. How NEC4's clause 53 final assessment changed final account practice.
Read guideProgramme Management
Clauses 31–32
Why the Accepted Programme is the most important document on any NEC4 project and what happens to CE assessments when you don't have one.
Read guideRecords & Compliance
Clause 52 & 11.2(26)
The records that underpin every payment application, CE quotation, and disallowed cost defence. What to capture and how to organise it.
Read guideContract Health Check
Compliance Audit
A seven-area audit framework for checking NEC4 compliance. RAG scoring, common findings, and how to build checks into project routines.
Read guide.webp)




