Key Takeaways

Know who notifies what

Some compensation events must be notified by the Project Manager, others by the Contractor. Get this wrong and you risk losing entitlement. Under clause 61.3 the Contractor has eight weeks from becoming aware of the event to notify. Missing that may prevent a change to the Prices or the Completion Date, but the bar is not absolute: it does not apply where the event arises from the Project Manager giving an instruction or notification, issuing a certificate or changing an earlier decision, and it bites only on events the Contractor is obliged to notify.

Timelines are limits, not targets

Three weeks to submit a quotation. Eight weeks to notify. One week for the PM to respond. These deadlines exist to maintain commercial clarity and prevent disputes. Acting early keeps the contract collaborative. Waiting until the last day makes everything adversarial.

Use assumptions to price uncertainty

When the impact of an event is unclear, the Project Manager should state assumptions under Clause 61.6. This lets contractors price fairly without building in excessive risk. If the assumption proves wrong, it triggers a new compensation event to adjust. Only PM assumptions carry this protection.

Document everything under Clause 13

Keep the required notifications, decisions and acceptances in the contractual form and communication system, with their dates and supporting records. A site diary or informal discussion does not replace a notice.

Further Reading

GMH Planning’s own guidance notes, CECA bulletins and webinar pages on this topic. They explain the standard provisions and are useful alongside, not instead of, the executed contract.

Check the contract form, edition, incorporated amendments, main and secondary options, Contract Data and any Z clauses for your own project.

Session Transcript
Read More

Audience Q&A