Key Takeaways

The contractor should prepare the activity schedule, not the client

Clients preparing the activity schedule risks misalignment with the contractor's delivery plan and cash flow needs. The NEC4 contract does not expect the client to produce it. If the client wants a tender comparison document, they should allow contractors to submit their own detailed activity schedule alongside it.

Under Option A, contractors only get paid for completed activities

Option A values completed activities or groups of activities under its payment definition, rather than applying a percentage-complete valuation to each item. Check the treatment of groups and Defects, the activity structure, other amounts due and any amendments.

Compensation events must be agreed promptly to protect cash flow

Changes to the Prices from compensation events follow implementation. Keep quotation and assessment procedures moving, and plan a suitable activity breakdown for significant changes. Payment still depends on the applicable option, activity structure and contract wording.

Option C activity schedules set the target but do not drive interim payments

Under Option C, the contractor is paid defined cost plus fee, not from the activity schedule. The activity schedule establishes the target price for the pain/gain share calculation. Despite this, parties should still keep the activity schedule updated to track their commercial position and avoid a widening gap between target and actual cost.

Further Reading

GMH Planning’s own guidance notes, CECA bulletins and webinar pages on this topic. They explain the standard provisions and are useful alongside, not instead of, the executed contract.

Check the contract form, edition, incorporated amendments, main and secondary options, Contract Data and any Z clauses for your own project.

Session Transcript
Read More

Audience Q&A