NEC4

NEC4 Roles & Responsibilities: Who Does What Under ECC

Under the NEC4 ECC, every named role carries specific contractual powers, duties, and obligations. Get this wrong — confuse who can give an instruction, miss who holds a response deadline, or misunderstand the limits of the Project Manager's authority — and the consequences range from invalid notices to unenforceable decisions.

Will Doyle

Will Doyle

27 February 2026 · 15 min read

The Project Manager: Powers, Duties, and Response Periods

The Project Manager (PM) is the most contractually active role under NEC4. Clause 14.2 allows the Employer to replace the Project Manager, but once appointed, the PM acts within the contract with significant autonomous authority. The PM is not the Employer's agent in the traditional sense — many PM decisions are binding on the Employer even where the Employer would prefer a different outcome.

What the PM can do:

  • Issue instructions that change the Works Information (Clause 14.3) — these are compensation events under Clause 60.1(1)
  • Accept or reject the Contractor's programme (Clause 31.3)
  • Notify and assess compensation events (Clauses 61, 62, 63)
  • Certify payments (Clause 51)
  • Issue take-over certificates (Clause 35)
  • Give instructions to stop or not start work (Clause 34)
  • Accept or reject early warning notifications and manage the Early Warning Register (Clause 15)

What the PM cannot do is equally important. The PM cannot unilaterally change the contract terms. The PM cannot instruct the Contractor to breach a legal obligation. And critically, the PM cannot withhold a certificate that the contract requires — doing so is a breach entitling the Contractor to compensation.

PM Response Periods That Matter Commercially

Miss these and you create deemed acceptance or breach situations:

PM Obligation Clause Period
Notify whether an event is a CE61.41 week from Contractor notification
Respond to CE quotation (accept/reject/assess)62.3/62.4Period for reply (typically 2 weeks — check Contract Data)
Respond to programme submission31.3Period for reply
Certify payment51.1Within 5 days of assessment date
Respond to early warning notification15.3At next EW meeting (must arrange promptly)

I've seen PM teams on large infrastructure packages routinely run past the Clause 61.4 one-week deadline. The Contractor lets it slide because the working relationship feels fine. Then a dispute arises six months later and the PM claims they never agreed the event was a CE at all. The Contractor has no deemed acceptance — because they never formally invoked it. Don't let that happen. Track PM deadlines from day one.

The Supervisor: Inspection Rights and What They Actually Mean

The Supervisor is appointed by the Employer and operates independently of the Project Manager. The key point most commercial teams miss: the Supervisor's role is quality assurance, not contract administration. The Supervisor cannot instruct the Contractor directly (except in very specific circumstances). Instructions come from the PM, not the Supervisor.

What the Supervisor can do:

  • Instruct the Contractor to uncover work (Clause 42.1)
  • Notify the Contractor of defects (Clause 42.2) — but the PM then manages the defect correction process
  • Attend tests and inspections
  • Issue a defects certificate when the defects correction period ends (Clause 43.3)

The Supervisor's defect notification under Clause 42.2 starts a clock. The Contractor has until the defects date to correct notified defects. Uncorrected defects after the defects date allow the PM (not the Supervisor) to assess the cost of having the Employer correct them under Clause 45.

One function the Supervisor cannot delegate: issuing the defects certificate. This must be done by the Supervisor personally. The defects certificate is a precondition for the Employer releasing the second portion of retention where Option X16 is used.

The Employer: Retained Risks and Direct Obligations

The Employer is a party to the contract but exercises most contractual authority through the PM. That said, the Employer retains several direct obligations that do not flow through the PM.

Direct Employer obligations under NEC4 ECC:

  • Provide access to and use of the Site as required by the Works Information (Clause 33) — failure is a CE under Clause 60.1(2)
  • Provide materials, facilities, and samples as stated in the Works Information (Clause 25.1)
  • Insure as required by Clause 84 and Options X13/X14
  • Pay the Contractor in accordance with the contract — the Employer cannot instruct the PM to withhold a certified payment

Here's something that trips up junior QS teams: the Employer and the PM are not interchangeable. On many projects, the Employer issues directions informally — emails, meeting notes, phone calls — that look like PM instructions. They are not. An Employer direction to the Contractor that is not channelled through the PM as a formal instruction under Clause 14 does not create a compensation event. The Contractor should always confirm with the PM in writing when an apparent Employer direction has commercial implications.

The Contractor: Core Obligations and Where Teams Go Wrong

The Contractor's obligations under NEC4 ECC are substantially more demanding than under traditional JCT or older NEC3 practice. The core obligation is to Provide the Works — defined by the Works Information — but the contract wraps this in procedural requirements that are commercially critical.

The Contractor's key obligations:

  • Provide the Works in accordance with the Works Information and the Site Information
  • Notify compensation events within 8 weeks of becoming aware (Clause 61.3) — the NEC4 eight-week time bar is a condition precedent
  • Submit and maintain a compliant Accepted Programme (Clauses 31 and 32)
  • Give early warnings of risks that could affect cost, time, or quality (Clause 15)
  • Submit CE quotations within 3 weeks of the PM's instruction to do so (Clause 62.2)
  • Notify the PM if the Contractor believes a PM instruction is not contractually valid (Clause 17)

Programme Obligations in Detail

The programme obligation is one of the most commercially significant — and most neglected. Clause 31 specifies what the programme must show: planned start and finish dates for operations, the Accepted Programme date, float, time risk allowances, planned Completion, and the order and timing of any operations the Contract Data requires. A programme that does not include all of these is not compliant and the PM is entitled to reject it.

Without an Accepted Programme, the PM assesses compensation event time impacts using their own assumptions under Clause 63.5. Those assumptions are invariably less favourable to the Contractor than the Contractor's own programme logic. The NEC4 programme management guide covers this in full.

Subcontracting Rules

The Contractor may subcontract work but must submit the name of each proposed Subcontractor to the PM for acceptance (Clause 26.2). The PM can only reject a proposed Subcontractor on stated grounds. Critically, for cost-reimbursable options (Options C, D, E), Defined Cost includes payments to Subcontractors — which means Subcontractor invoices feed directly into the Contractor's cost calculation. Inflated or unapproved Subcontractor costs create disallowed cost risk.

The Subcontractor: Flow-Down Obligations

NEC4 does not define a mandatory subcontract form, but the NEC4 Engineering and Construction Subcontract (ECS) is designed to flow down the main contract's key mechanisms. Where it is used, the Subcontractor faces the same time bar, early warning, programme, and communication requirements as the Contractor faces on the main contract.

What flows down under NEC4 ECS:

  • 8-week time bar for compensation events (mirrored from Clause 61.3)
  • Early warning obligations
  • Programme submission and acceptance
  • Defects notification and correction periods
  • Formal communication requirements

The practical risk is where a Contractor is using a JCT subcontract or a bespoke form alongside an NEC4 main contract. The mechanisms do not align cleanly. Contractors who mix contract forms on NEC4 projects create gaps that are expensive in disputes.

Design Responsibility: Where It Sits Under Different ECC Options

Under NEC4 ECC, design responsibility depends on the Works Information. The contract does not allocate design responsibility by default — the Works Information must state explicitly what the Contractor is to design and what design the Employer has provided.

ECC Option Typical Design Split Key Clause
Option A (Lump Sum)Can be Contractor-designed, Employer-designed, or splitWorks Information
Option B (Lump Sum with BoQ)Usually Employer-designed (BoQ implies detailed design)Works Information
Option C (Target Cost)Often split or Contractor-designed elementsWorks Information
Option D (Target Cost with BoQ)Often Employer-designed frameworkWorks Information
Option E (Cost Reimbursable)Flexible — defined by Works InformationWorks Information
Option F (Management Contract)Contractor procures; design usually Employer or SubcontractorWorks Information

Where the Contractor provides design, Clause 21.1 requires the Contractor to design to the standard of skill and care of a professional designer. There is no fitness for purpose obligation unless the Works Information explicitly imposes one. Where the Employer provides design through a separate consultant or Other Person, that person's errors are Employer risk under Clause 60.1(1) — an instruction to change the Works Information to correct a design error is a compensation event.

NEC4 allows the Employer to engage Other Persons who work alongside the Contractor on the site. If an Other Person delays the Contractor's work or causes an instruction to change the Works Information, that is a compensation event under Clause 60.1. The Contractor who identifies these interactions early — and gives early warning notifications about interface risks — is in a much stronger position than one who absorbs the disruption and claims retrospectively.

The Adjudicator: Appointment and Powers Under W1 and W2

NEC4 ECC includes dispute resolution through adjudication under two alternative Dispute Resolution Options:

  • Option W1 — applies where the Housing Grants, Construction and Regeneration Act 1996 does not apply (typically offshore or certain utilities works)
  • Option W2 — applies where the HGCRA does apply (the default for most UK construction contracts)

Under W2 (the more common option), either party may refer a dispute to adjudication at any time, with the adjudicator required to reach a decision within 28 days of referral (extendable by 14 days with the referring party's consent).

What the adjudicator can decide:

  • Whether a compensation event has occurred
  • The correct assessment of a compensation event
  • Whether the PM has acted correctly in accepting or rejecting a programme
  • Whether the time bar has been validly applied
  • Payment disputes

The adjudicator's decision is binding until the dispute is resolved by a tribunal. The "pay now, argue later" principle means that an adjudicator's payment decision must be implemented even if one party disagrees. One point that often catches out Employers: the PM's certificates are not binding on the adjudicator. The adjudicator can override a PM assessment if the PM has acted incorrectly under the contract.

How the Roles Interact: PM Instructions vs Employer Directions

The most practically important relationship to understand is between the Employer and the PM. The Employer appoints the PM and can replace them (Clause 14.2), but the PM's contractual decisions are not subject to Employer override once made. If the PM certifies a payment, the Employer must pay. If the PM accepts a programme, the Employer cannot instruct the PM to un-accept it.

This creates a real dynamic on large projects: the Employer's commercial team will often try to influence PM decisions informally. The PM who simply acts on these instructions without applying their contractual judgement is exposing the Employer to an unfavourable adjudication outcome.

Worked Example

£55M Highways Maintenance Package, East Midlands

The situation

The Contractor received a verbal instruction from the Employer's design team (an Other Person) to change the drainage specification on a 2.4km section of carriageway. The Contractor's site team implemented the change without seeking a formal PM instruction. The additional cost was approximately £340,000.

The dispute

When the Contractor raised CE-034 twelve weeks later, the PM rejected it. The PM argued the direction had not been channelled through the correct contractual route. The Contractor argued it was acting on Employer direction.

The adjudication outcome (January 2025)

The adjudicator found: (1) the Employer's design team were Other Persons under the Works Information; (2) their direction was not a PM instruction under Clause 14; (3) however, the PM had subsequently included the changed specification in revised Works Information — constituting a retrospective instruction; (4) the CE clock ran from the PM's revised Works Information, not the original verbal direction. The Contractor recovered £310,000. The £30,000 loss was attributable to costs incurred before the PM's revised Works Information was issued.

The lesson: understand who has authority to instruct you. When anyone other than the PM gives you a direction that has cost implications, confirm it in writing with the PM before implementing it.

What Happens When the PM Gets It Wrong

The PM is a person, not an oracle. PM decisions can be wrong, and the contract provides for this:

  • If the PM fails to notify a CE that should have been notified, Clause 61.1 gives the PM the obligation to notify CEs it should have raised
  • If the PM wrongly applies the time bar, the Contractor can adjudicate
  • If the PM assesses a CE incorrectly, the Contractor can ask the PM to reassess (Clause 62.4) or refer to adjudication
  • If the PM fails to certify a payment correctly, the Contractor can refer to adjudication and seek enforcement

Reference: NEC4 Roles Comparison Table

Role Appointed by Key Powers Key Obligations Can Delegate?
Project ManagerEmployerInstructions, CE assessment, payment certification, take-overNotify CEs, certify payments, respond within deadlinesMost functions — but not PM-specific certificates
SupervisorEmployerInspections, defect notifications, defects certificateNotify defects, issue defects certificateMost — not the defects certificate itself
EmployerParty to contractReplace PM/Supervisor, payProvide access, pay on time, provide Employer-designN/A
ContractorParty to contractSubcontract (with PM approval), propose AdjudicatorNotify CEs, maintain programme, give early warningsMost — retains liability
SubcontractorContractor (PM approval needed)Perform subcontracted workBack-to-back obligations, early warnings, programmeDepends on subcontract form
AdjudicatorContract Data or nominating bodyDecide disputesAct impartially, decide within 28 days (W2)No

1. Treating Supervisor instructions as PM instructions. The Supervisor does not have authority to vary the works. An instruction to uncover and retest work is not an instruction to carry out additional work. The Contractor should seek a PM instruction for any additional cost arising from Supervisor-directed activities.

2. Accepting informal Employer directions as contractual instructions. Every direction with cost or time implications needs to be channelled through the PM. If the Employer's commercial team tells you informally to accelerate, ask the PM for a formal acceleration instruction under Clause 36.

3. Not tracking PM response deadlines. The PM has binding response periods. Many contractors do not log when these expire. A PM who has missed the Clause 61.4 one-week deadline has not prevented a valid CE — but the Contractor who fails to invoke deemed acceptance under Clause 62.6 misses a concrete commercial advantage.

4. Assuming the PM and Employer are aligned. Sometimes they're not. The PM has an obligation to act in a spirit of mutual trust and cooperation under Clause 10.2. The Employer's commercial interests may push against this. Understanding the tension helps the Contractor understand why PM decisions sometimes don't make commercial sense from the Employer's perspective — and why adjudication can overturn them.

5. Failing to get proposed Subcontractors accepted. Under Clause 26.2, the PM must accept proposed Subcontractors before they are engaged. A Contractor who subcontracts without this acceptance risks the work being treated outside the contract framework and the costs being Disallowed Cost under Option C or D contracts.

Gather's QS AI Agent ensures every site diary entry is categorised correctly — giving your commercial team the contemporaneous records that support CE notifications, programme compliance, and early warning responses at every stage of the NEC4 process.

NEC4 Explained

Frequently Asked Questions

Who is the Project Manager under NEC4 and what is their role?

The Project Manager is a named individual appointed by the Employer to administer the NEC4 contract on the Employer's behalf. The PM has autonomous authority to issue instructions, assess compensation events, certify payments, and accept or reject the Accepted Programme. The PM is not simply the Employer's representative — many PM decisions bind the Employer without the Employer's specific approval for each decision.

Can the Supervisor give instructions to the Contractor?

The Supervisor's authority is limited to quality assurance functions. Under Clause 42.1, the Supervisor can instruct the Contractor to uncover work for inspection. Beyond that, the Supervisor notifies defects but cannot instruct the Contractor to carry out additional work or vary the scope. All scope-changing instructions must come from the Project Manager.

What is the difference between the PM and the Employer under NEC4?

The Employer is a party to the contract; the PM is the Employer's representative appointed to administer it. The PM has contractual authority that the Employer cannot override once exercised — if the PM certifies a payment, the Employer must pay. The Employer's direct obligations include providing site access (Clause 33) and paying on time. Employer directions to the Contractor that are not channelled through the PM as formal instructions do not create compensation events.

Does the Subcontractor need to follow NEC4 processes?

Where an NEC4 Engineering and Construction Subcontract (ECS) is used, yes — the Subcontractor faces equivalent obligations for early warnings, compensation event notification (with an 8-week time bar), programme submission, and formal communications. Where a bespoke or JCT-form subcontract is used, the back-to-back obligations depend on the specific drafting. On NEC4 main contracts, misaligned subcontract forms create interface gaps that are expensive in disputes.

What happens if the Project Manager applies the time bar incorrectly?

The Contractor can refer the dispute to adjudication. If the PM has wrongly applied the Clause 61.3 time bar — for example, where the PM should themselves have notified the event under Clause 61.1, or where the Contractor genuinely was not aware of the event until a later date — the adjudicator can overturn the PM's decision and reinstate the Contractor's entitlement.

Who appoints the Adjudicator under NEC4?

The Adjudicator is named in the Contract Data at the outset of the contract. Where no adjudicator is named or the named adjudicator is unable to act, the nominating body specified in the Contract Data appoints a substitute. Under Option W2 (the standard UK option), either party can refer a dispute to adjudication at any time without notice.

What are the Contractor's programme obligations under NEC4?

Under Clause 31, the Contractor must submit a programme that shows planned operations, dates, the Accepted Programme date, float, time risk allowances, and planned Completion. The PM can only reject a programme if it does not comply with the contract requirements — rejection must state the reason. Without an Accepted Programme, compensation event time impacts are assessed by the PM using their own assumptions under Clause 63.5, which consistently disadvantages the Contractor. The programme should be treated as a commercial document, not just a project management tool.

Can the Employer replace the Project Manager mid-contract?

Yes. Clause 14.2 allows the Employer to replace the PM (and the Supervisor), but only after giving notice to the Contractor. The replacement is effective once the Contractor has received the notice. A change of PM does not change the contract terms — all decisions, accepted programmes, and certified payments made by the outgoing PM remain in effect.

Contract administration, assured

Ensure Your NEC4 Contract Administration Is Commercially Watertight

Gather's QS AI Agent analyses every site diary entry against NEC4 clause 60.1 categories and records CE awareness dates — giving your commercial team the contemporaneous evidence base that supports CE notifications, programme compliance, and early warning responses. Every role does their job when the records are right.

40% more compensation events identified vs manual review

Deliver NEC projects better Free 20-min demo
Book demo