NEC4

Concurrent Delay Under NEC4: What It Means and How to Protect Your Position

Concurrent delay under NEC4 is handled through the compensation event mechanism, programme obligations, and float rules — not a standalone rule. This guide covers float ownership, programme analysis, case law, and the practical steps your commercial team should take.

Will Doyle

Will Doyle

26 February 2026 · 13 min read

Concurrent delay is one of the most contested areas in construction law — and under NEC4, it's handled very differently from JCT or FIDIC. If you're managing an NEC4 contract and your project is in delay, understanding exactly how NEC4 treats concurrent causation determines whether your extension of time claim succeeds, gets reduced, or collapses entirely.

This guide covers the definition, the contractual mechanism, float ownership, programme analysis, and the practical steps your commercial team should take before a concurrent delay dispute reaches adjudication.

What Is Concurrent Delay?

Concurrent delay arises when two or more independent causes of delay — one attributed to the client (or a compensation event), one attributed to the contractor — are operating simultaneously, and each would on its own have caused delay to completion.

The definition sounds simple. In practice, it's a mess. Courts and adjudicators have spent decades arguing about whether "true concurrency" requires exact calendar overlap, whether delays on different activities count, and what the appropriate remedy should be when you can't cleanly separate the causes.

The Society of Construction Law Delay and Disruption Protocol (2nd edition, 2017) defines concurrent delay as: "a period of project overrun which is caused by two or more effective causes of delay which are of approximately equal causative potency." That phrase — "approximately equal causative potency" — does a lot of heavy lifting, and it's almost never straightforward to establish on a live project.

What matters for NEC4 teams is this: the contract doesn't use the phrase "concurrent delay" at all. It never mentions it. Instead, the ECC handles the underlying situation through its compensation event mechanism, programme obligations, and float rules — and the outcomes are often different from what practitioners expect when they arrive from a JCT background.

How NEC4 Handles Concurrent Delay Differently

Under JCT, concurrent delay typically results in the contractor getting an extension of time (because the employer risk event is a ground for EOT) but no loss and expense (because the contractor's own default contributed equally). That's the "extension but no money" outcome most commercial managers know.

NEC4 doesn't work that way.

The Compensation Event Mechanism

Under NEC4, an extension of time is not granted as a stand-alone right. Time is dealt with as part of a compensation event assessment under Clause 60. The Contractor notifies a compensation event, submits a quotation under Clause 62 showing both the time and cost impact, and the Project Manager accepts, rejects, or assesses it.

The key question in a concurrent delay scenario is: does the compensation event cause delay to the Completion Date? Under Clause 63.3, a compensation event assessment includes a delay to the Completion Date only if the event affects the critical path of the Accepted Programme. If the contractor's own delay has already pushed a particular sequence off critical path, the Client risk event may have no demonstrable effect on Completion — even if the contractor is genuinely suffering its impact.

This is where the absence of an Accepted Programme becomes financially catastrophic in concurrent delay situations. Without an accepted, updated programme showing the critical path at the time of the event, there's no baseline against which to measure the event's impact. The Project Manager assesses using their own assumptions under Clause 63.1 — and those assumptions will almost always attribute less delay to the compensation event than the contractor believes is fair.

Float Belongs to the Project

This is the single most important difference between NEC4 and most other standard forms.

Under Clause 63.3, a compensation event is assessed as the difference between the Accepted Programme (including any terminal float) and the revised programme incorporating the event. The contract is silent on who "owns" float in the traditional sense — because in NEC4, the question barely arises.

Here's why. NEC4 requires the Accepted Programme to show all float (Clause 31.2). Total float is visible to both parties. When a compensation event is assessed, it's assessed against the programme as it stands. If there was 3 weeks of total float on the affected sequence and the compensation event consumes 2 weeks of it, the assessment grants 0 weeks of extension — because the Completion Date hasn't moved.

I've seen this genuinely surprise senior commercial managers arriving from JCT backgrounds. They expect float to be a contractor-owned resource. Under NEC4, it isn't. Both parties can see it, and the mechanism consumes it before granting any EOT.

The practical consequence: a contractor who maintains programme float carefully is more exposed to concurrent delay arguments, because that float absorbs Client-risk events before they reach the critical path. A contractor who has already consumed their float through their own performance issues has — somewhat counterintuitively — a stronger case that the compensation event directly caused critical delay.

Contractor-Owned Risk Events

Under Clause 60.1, there are 19 categories of compensation event. Everything outside those 19 categories is a contractor risk. If the contractor is in delay due to a contractor risk event (say, a subcontractor resource failure), that delay does not entitle them to an extension of time or additional cost.

When a Client-risk event and a contractor risk event are both operating, the question becomes: which one is driving delay to completion? NEC4 doesn't provide a statutory answer. The contract requires an honest programme analysis to determine causation — and that programme analysis is only meaningful if the Accepted Programme is current and compliant.

Worked Example: Two Delays, One Programme

Worked Example

£45M Rail Infrastructure Package, NEC4 Option C

The scenario

Completion Date: 14 November 2025. Accepted Programme accepted at week 12, showing 6 weeks of total float on the critical path.

Week 22 — Client risk event

The Project Manager issues a late design instruction (Clause 60.1(1)) affecting track formation on Section 4. The instruction is 4 weeks late against the required information date on the Accepted Programme. The contractor notifies CE-027 on 3 March 2025.

Week 22 — Contractor risk event (same period)

The contractor's earthworks subcontractor fails to resource Section 3 adequately. Section 3 feeds directly into Section 4. The subcontractor's under-resourcing is causing a 3-week delay on its own sequence.

The programme analysis

At the point of the compensation event (3 March 2025), the Accepted Programme shows Section 3 on the critical path with a 3-week contractor-caused overrun. Section 4 was 2 weeks behind critical path (consuming part of the 6-week total float). The CE assessment under Clause 63 works from the Accepted Programme at the dividing date. The critical delay to completion is the 3-week subcontractor delay on Section 3. Even accounting for the 4-week instruction delay on Section 4, Section 4 cannot start until Section 3 completes — so the critical path is driven by the contractor risk event.

The outcome

CE-027 grants additional Defined Cost for the design instruction work, but no extension to the Completion Date — because the critical delay at the dividing date is the contractor's own subcontractor failure. After week 28, when the subcontractor completes Section 3, the design instruction moves onto the critical path and CE-027 can be revised.

This is why concurrent delay under NEC4 is a moving target. It isn't decided at one point in time. It requires programme analysis at multiple assessment points.

The Case Law Position

NEC4 concurrent delay hasn't generated the volume of case law that JCT has, partly because the contract is newer and partly because many NEC4 disputes resolve in adjudication rather than litigation. But several key cases inform how these situations play out.

Henry Boot Construction v Malmaison Hotel (1999): While a JCT case, it established the principle that where there are two concurrent causes of delay — one an employer risk event, one a contractor risk event — the contractor is entitled to an EOT for the employer risk even if the contractor's own default would have caused equal delay. This "malmaison approach" does not directly apply under NEC4 (because NEC4 doesn't have a standalone EOT mechanism), but it informs how adjudicators think about causation.

North Midland Building v Cyden Homes (2018): The Court of Appeal confirmed that parties can contract out of the malmaison approach — and that a clause giving the contractor no EOT where concurrent delay exists is enforceable. Under NEC4, where the compensation event mechanism handles time prospectively against the programme, a similar result can occur without needing an express exclusion clause. The programme analysis determines causation, not a judicial default rule.

Walter Lilly v Mackay (2012): Akenhead J held that the contractor is entitled to an EOT if a relevant event (employer risk) caused delay, even if there was concurrent contractor default. Again a JCT case, but the factual analysis methodology — requiring an honest, critical-path-based assessment — is directly applicable to NEC4 programme analyses.

Saga Cruises BDF v Fincantieri SpA (2016): In an arbitration context, this case addressed the problem of concurrent delay where neither cause could be separated from the other. The principle that emerged — apportion where possible, but not where causes are genuinely inseparable — maps onto NEC4's requirement for honest programme analysis rather than mechanical apportionment.

The honest truth? There is no definitive NEC4 concurrent delay case that has settled the question at appellate level. Adjudicators apply their own experience and the programme evidence before them. Which means the quality of your programme and records is everything.

Programme Analysis Methods

Three methods dominate in practice. Your choice matters because adjudicators and experts will scrutinise the methodology, not just the conclusions.

Time Impact Analysis (TIA)

The preferred method for NEC4 disputes. TIA inserts the delaying event into the Accepted Programme at the point it occurred and models the resulting impact on the critical path. For each compensation event, it asks: "If I run the programme as it stood at the event date, with this event added, what happens to completion?"

TIA respects NEC4's prospective assessment basis (Clause 63 requires assessment from the dividing date). It produces a contemporaneous result that mirrors what the contract requires. Under NEC4, TIA is the correct methodology for compensation event quotations.

The challenge: TIA only works if you have an Accepted Programme that was genuinely current at the time of the event. Programmes submitted but not accepted, or accepted but not updated for months, produce a baseline that both parties can attack.

Windows Analysis

Divides the project into time windows and analyses delay causes within each window. Useful where multiple overlapping events need to be separated. Less well-aligned with NEC4's prospective assessment basis but widely used in adjudication where TIA isn't possible because of programme deficiencies.

As-Planned vs As-Built

Compares the original programme to what actually happened. Simple to explain. Frequently challenged because it doesn't account for the sequence in which events occurred or the critical path logic at specific points in time. This method tends to obscure concurrent delay rather than resolve it — I'd be cautious about relying on it in an NEC4 adjudication.

Common Mistakes in Concurrent Delay Situations

1. Not notifying CEs because "the delay is our fault anyway." Even where the contractor believes there's concurrent delay that weakens their position, the compensation event must still be notified within 8 weeks of awareness under Clause 61.3. If you don't notify, you lose the entitlement entirely — not just in terms of EOT, but also additional Defined Cost. Don't let a concurrent delay argument be an excuse for missing the eight-week time bar.

2. Failing to raise early warnings for contractor-risk delays. Under Clause 15, the contractor must raise an early warning for any matter that could affect the Completion Date — including contractor-caused delays. Failure to raise an early warning for the contractor's own subcontractor problems looks evasive in adjudication and can affect the adjudicator's assessment of who caused what and when. The early warning process is a protection mechanism, not just a Client-event trigger.

3. Letting the Accepted Programme fall out of date. An outdated programme gives the Project Manager unilateral discretion under Clause 63.1. You cannot mount a credible concurrent delay defence — or a credible concurrent delay offence — without a current, accepted programme. The NEC4 programme management guide covers what a compliant programme must show.

4. Assuming concurrent delay is binary. "There's concurrent delay, so we get nothing." That's wrong. The compensation event may still entitle the contractor to additional Defined Cost for the work required by the Client-risk event, even if no EOT is granted. Under Options C and D (target cost), the cost is still shared through the pain/gain mechanism. Don't write off the cost element of a CE just because the EOT argument is weak.

5. Not running programme analysis until the dispute is live. By then, it's too late to produce a contemporaneous analysis. TIA requires contemporaneous programme snapshots. If you haven't saved P6 or Asta programme files at each update cycle, you can't reconstruct what the critical path looked like in March when the CE happened. Programme analysis should be part of your monthly commercial review, not a retrospective exercise after the claim is rejected.

NEC4 Concurrent Delay Quick Reference

Issue NEC4 Position Key Clause
How EOT is grantedOnly as part of CE assessment; no standalone EOTClause 62–63
Float ownershipProgramme float visible to both parties; not contractor-ownedClause 31.2, 63.3
Causation testCritical path impact at the dividing dateClause 63
No Accepted ProgrammePM assesses using own assumptionsClause 63.1
CE notification despite concurrent delayStill required within 8 weeks of awarenessClause 61.3
Early warning obligationApplies to contractor-caused delays tooClause 15
Cost entitlement in concurrent delayMay still exist even where EOT is nilClause 63
Programme analysis methodTime Impact Analysis preferredClauses 31, 32, 63

Practical Steps for Commercial Teams

Before the concurrent delay arises:

  • Maintain an Accepted Programme that is submitted and accepted at every 4-week update cycle
  • Save programme files at each submission — you need the contemporaneous snapshots
  • Run the CE register weekly and cross-reference open CEs to the current programme's critical path
  • Raise early warnings for contractor risk events as well as Client risk events

When concurrent delay is suspected:

  • Notify the compensation event immediately — do not wait to resolve the concurrent delay question first
  • Commission a TIA at the point of the CE notification, based on the current Accepted Programme
  • Record site conditions daily in sufficient detail to support the programme analysis — resources deployed, areas affected, and causal event cross-referenced to the CE number

When the CE quotation is prepared:

  • Show both the cost element and the time element separately
  • If the TIA shows nil EOT (because the critical path is driven by a contractor risk event), state that explicitly in the quotation and explain why
  • Include the programme analysis as an attachment to the quotation

If the PM disputes the concurrent delay position:

  • Request the PM's programme analysis in writing
  • Challenge any assumptions the PM makes under Clause 63.1 that aren't grounded in the Accepted Programme
  • Consider instructing a delay expert early if the amounts are significant

Gather's QS AI Agent analyses every site diary entry against NEC4 clause 60.1 categories. Every CE is flagged with the awareness date recorded — giving your commercial team the contemporaneous evidence base that concurrent delay analysis depends on.

NEC4 Explained

Frequently Asked Questions

Does NEC4 address concurrent delay explicitly?

No. The NEC4 Engineering and Construction Contract does not use the phrase "concurrent delay." The contract handles the underlying situation through its compensation event assessment mechanism (Clause 63), the Accepted Programme obligations (Clauses 31 and 32), and the principle that assessments are made from the dividing date. The outcome in a concurrent delay scenario is determined by programme analysis, not by any express contractual rule about how to apportion liability.

Who owns float under NEC4?

Float under NEC4 is a contractual resource visible to both parties, not a contractor-owned commercial buffer. Under Clause 31.2, the Accepted Programme must show all float. Under Clause 63.3, a compensation event is assessed by reference to the Accepted Programme — meaning total float on the affected sequence is consumed before any extension to the Completion Date is granted. This differs from JCT, where float ownership is often disputed and some courts have treated it as belonging to the contractor.

Can a contractor get an extension of time even with concurrent delay under NEC4?

It depends entirely on the programme analysis. If the compensation event drives the critical path at the time of assessment, the contractor is entitled to an extension equal to the critical delay caused by the event — even if there are other concurrent contractor-caused delays operating on non-critical sequences. If the critical path is driven by the contractor's own delay at the time of assessment, the compensation event may grant no EOT. The assessment is dynamic: as the programme evolves, the critical driver can change.

What is the dividing date and why does it matter for concurrent delay?

The dividing date is the point in time before which actual Defined Cost is used in a CE assessment and after which forecast Defined Cost is used. Under Clause 63, the assessment is made prospectively from the dividing date — meaning it assesses what the programme impact should be based on what was known at that point, not what subsequently happened. For concurrent delay analysis, the critical path position at the dividing date determines whether the CE grants an EOT. The dividing date guide explains this in detail.

Does concurrent delay affect the cost element of a compensation event?

Not automatically. The time and cost elements of a CE quotation are separate. Even where a concurrent delay argument means the CE grants no EOT, the compensation event may still entitle the contractor to additional Defined Cost for the extra work caused by the Client risk event. Under Options C and D, that cost flows through the target and affects the pain/gain share. Don't conflate the EOT argument with the cost entitlement — they're assessed independently under Clause 63.

How does the early warning mechanism interact with concurrent delay?

Early warnings are required for any matter that could affect the Completion Date (Clause 15.1) — including contractor-caused delays. If a contractor fails to raise an early warning for their own delay and that delay contributes to a concurrent situation, the Project Manager can invoke Clause 63.7 in relation to any CE whose impact was exacerbated by the lack of early warning. A contractor who has issued contemporaneous early warnings for both the Client-risk events and their own risks is in a much stronger position in adjudication.

What case law applies to concurrent delay under NEC4?

The directly applicable NEC4 concurrent delay case law is limited. Adjudicators draw on: (1) the SCL Delay and Disruption Protocol (2017); (2) JCT cases including Henry Boot v Malmaison (1999), Walter Lilly v Mackay (2012), and North Midland Building v Cyden Homes (2018); and (3) general construction law principles around burden of proof and programme analysis methodology. The contractor bears the burden of proving that the compensation event caused delay to the Completion Date.

Programme records, assured

Build the Contemporaneous Evidence Base That Concurrent Delay Analysis Requires

Gather's QS AI Agent analyses every site diary entry against NEC4 clause 60.1 categories, recording the awareness date for every event. When concurrent delay arises, your commercial team has the contemporaneous programme and records evidence that TIA depends on — captured at the time, not reconstructed months later.

40% more compensation events identified vs manual review

Deliver NEC projects better Free 20-min demo
Book demo