Key Takeaways

Disallowed cost is a commercial control mechanism, not a penalty

Read the definition for the applicable main option. Options C, D and E use clause 11.2(26); Option F has separate wording. Cost records support substantiation, but do not make a cost recoverable if another exclusion applies.

The scope is referenced in 30+ places in the conditions of contract

Ben counted around thirty to thirty-two places in the conditions of contract that rely on a statement in the scope. Disallowed cost hinges on several of them: the form of the application for payment, the procurement procedure, the constraints on how the work is done, and the definition of completion. Sort the scope before you start, not in the middle of the first payment cycle.

Build payment applications jointly with the project manager

Review the supporting records, forecast and assessment with the Project Manager before the payment deadline. This may resolve queries earlier, but does not replace the contractual application, assessment, certification and notice requirements.

Analyse the consequence of a missed early warning

Apply the causal test in the relevant Disallowed cost definition. The compensation event assessment consequences of a missed early warning are a separate question. Giving a warning does not transfer all cost risk to the Project Manager.

Session Transcript
Read More

Audience Q&A