NEC4 Disallowed Cost Explained

In Episode 9 of the NEC4 Webinar Series with CECA, Ben Walker and Glenn Hide explore disallowed cost under main options C, D and E (with a brief look at option F). They walk through why disallowed cost exists as a commercial control mechanism in cost-reimbursable contracts, where it sits in the payment assessment process, and unpack each of the six categories defined in clause 11.2(26). David Allen from CECA Southern adds the contractor's perspective on how good records, early warnings, and collaboration with the project manager are the most reliable ways to avoid disallowed cost in practice.

Presented By
Ben Walker
Ben Walker
Gather
Glenn Hide
Glenn Hide
GMH Planning
Key Takeaways

Disallowed cost is a commercial control mechanism, not a penalty

Disallowed cost only exists in the cost-reimbursable options (C, D, E and F), not in the priced options (A and B). Its purpose is to keep the contractor in check on cost-based contracts, where they would otherwise be paid for whatever they spend. The most common reason costs get disallowed is insufficient or inadequately detailed records, not deliberate misuse of the clause.

The scope is referenced in 30+ places in the conditions of contract

Ben counted around thirty to thirty-two places in the conditions of contract that rely on a statement in the scope. Disallowed cost hinges on several of them: the form of the application for payment, the procurement procedure, the constraints on how the work is done, and the definition of completion. Sort the scope before you start, not in the middle of the first payment cycle.

Build payment applications jointly with the project manager

The most successful teams treat the formal application and certification as a formality. They have already worked together on the forecast, the programme, and the records that support both. Payments still pass through the contractual machinery (clauses 50.1, 50.3, 51.1), but disagreements get resolved before the certificate is issued, not after.

Early warnings are cheap insurance against disallowed cost

The third category of disallowed cost (procedural failures) includes failure to give an early warning the contract required. The hypothetical 'what would you have done?' argument is hard to win on the back foot. If in doubt, share the early warning. It puts the decision and the consequence on the project manager, not on the contractor's bottom line.

Session Transcript
Download PDF
Read More
Audience Q&A

Heading 1

Heading 2

Heading 3

Heading 4

Heading 5
Heading 6

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur.

Block quote

Ordered list

  1. Item 1
  2. Item 2
  3. Item 3

Unordered list

  • Item A
  • Item B
  • Item C

Text link

Bold text

Emphasis

Superscript

Subscript

Audience Q&A

Excel / PowerBI
MCP Server
Aconex