NEC4

NEC4 Records and Compliance: What to Keep, How to Keep It, and Why It Matters

NEC4 records compliance is not optional paperwork. It is the foundation that determines whether you recover your full contractual entitlement or leave hundreds of thousands of pounds on the table.

Will Doyle

Will Doyle

17 February 2026 · 8 min read

Every commercial manager has lived this moment. A compensation event is legitimate, the entitlement is clear, and the NEC4 contract supports the claim. But when the Project Manager asks for substantiation, the records are incomplete, contradictory, or missing entirely. The entitlement evaporates.

NEC4 records compliance is what separates contractors who recover their full entitlement from those who settle for less. The contract does not prescribe a specific record-keeping system, but it creates obligations and consequences that make robust contemporaneous records a commercial necessity.

Why Records Matter Under NEC4

NEC4 operates on a principle that distinguishes it from traditional contracts: prospective assessment. When a compensation event occurs, the Contractor must demonstrate its effect on the Defined Cost and the programme from the dividing date forward. That forecast needs a credible baseline, and that baseline comes from records.

Records serve three distinct purposes under NEC4:

  • Substantiation of quotations. Under clause 62.2, the Contractor's quotation must show the changes to the Prices and any delay to the Completion Date. The Project Manager needs enough detail to assess the quotation. Without records of labour, plant, and materials deployed before and during the event, quotations become guesswork.
  • Defence against disallowed cost. Under the Disallowed Cost definition in clause 11.2(26), cost is disallowed if the Contractor cannot demonstrate it is justified. Records are the evidence that prevents legitimate Defined Cost from being stripped out at assessment.
  • Programme integrity. The Accepted Programme under clauses 31 and 32 is the objective baseline for delay and disruption analysis. Maintaining records that track actual progress against the programme is essential for demonstrating impact.

The Commercial Reality

On a typical £50 million NEC4 project, 3% of the Prices arise from compensation events. That is £1.5 million in entitlement. Contractors with poor records routinely leave a significant portion of that figure on the table. The entitlement existed. The records to prove it did not.

What Records the Contractor Must Keep

NEC4 does not contain a clause titled "Records to Maintain." Instead, the record-keeping obligations are embedded across multiple clauses, each creating a specific need. Understanding those needs prevents the common mistake of keeping records for their own sake rather than for a contractual purpose.

Under Options C, D, and E (target and cost-reimbursable contracts), the obligations are stronger still. The Contractor must keep accounts and records of Defined Cost that are open to the Project Manager's inspection at any time. This makes contemporaneous, auditable records a contractual requirement rather than a best practice recommendation.

Record TypeNEC4 ClausePurposeMinimum Frequency
Daily site diaryImplied (Cl. 61.3, 62.2)Contemporaneous narrative establishing awareness dates and supporting quotationsDaily
Labour allocation63.1 (Defined Cost)Substantiate people cost in CE quotationsDaily
Plant records63.1 (Defined Cost)Substantiate equipment cost and utilisationDaily
Material deliveries63.1 (Defined Cost)Link material cost to specific activitiesPer delivery
Photographic evidence60.1(12) physical conditionsVisual proof of conditions encounteredDaily + event-triggered
Weather records60.1(13) weatherCompare actual weather against 1-in-10-year thresholdDaily
Progress records32.1 (programme)Track actual vs planned progress for Accepted Programme updatesWeekly
Correspondence log13.1 (communications)Audit trail of notifications, instructions, and repliesContinuous
Subcontractor records26 (subcontracting)Substantiate subcontract Defined CostPer application

The relationship between records and compensation events is direct. Consider the lifecycle of a typical compensation event and where records are required at each stage.

01

Awareness and notification. The Contractor must notify the Project Manager within eight weeks of becoming aware that an event has happened or is expected to happen. Site diary entries establish the date of awareness. Without a diary entry, the Contractor cannot prove when awareness arose, and the Project Manager can argue the notification is time barred under clause 61.3.

02

Quotation preparation. The Contractor submits a quotation showing the effect on Defined Cost and any delay to the Completion Date. Labour allocation sheets, plant returns, and material records from the period before the event establish the baseline. Records from during and after the event show the impact. The difference is the entitlement.

03

Project Manager assessment. If the Project Manager makes their own assessment under clause 64, the Contractor's records provide the counterargument. Well-structured records make it difficult for the Project Manager to assess at a lower figure without justification.

04

Adjudication or dispute resolution. If agreement cannot be reached, the adjudicator relies on contemporaneous records above all other evidence. Retrospective witness statements carry far less weight than a diary entry written on the day the event occurred.

Worked Example

A Project Manager instructs a change to the Scope on 15 March. The Contractor's site diary records the instruction, the affected work area, and the labour and plant on site that day. The allocation sheet shows 12 operatives and a 20-tonne excavator deployed to the affected area. The Contractor notifies the compensation event on 17 March, within the eight-week time bar.

When preparing the quotation, the Contractor compares labour and plant records from the week before the instruction (baseline) against the four weeks after. The records show an additional 4 operatives and 1 telehandler deployed for 18 working days. The Defined Cost impact is calculated at £47,200. Without those daily records, the Contractor would be estimating, and the Project Manager would have grounds to reduce the assessment.

Poor Records and Disallowed Cost

The consequences of inadequate records under NEC4 are not theoretical. Disallowed cost under clause 11.2(26) applies to any cost that the Contractor cannot demonstrate is justified. In practice, this means the Project Manager can strip out cost items from payment applications and compensation event assessments if the Contractor cannot produce supporting records.

Record GapConsequenceTypical Financial Impact
No daily diary entriesCannot prove awareness date for CE notificationEntire CE time barred
Missing labour allocationCannot substantiate people cost in quotationSignificant reduction in assessed Defined Cost
No photographic evidenceCannot prove physical conditions for Clause 60.1(12)Physical conditions CE rejected
Inconsistent programme updatesCannot demonstrate delay impactExtension of time refused
No weather recordsCannot compare against 1-in-10-year thresholdWeather CE unsupported

Adjudicator Perspective

In adjudication, the party with the better records almost always wins. Adjudicators have 28 days to reach a decision. They rely on contemporaneous evidence because it is objective. A well-maintained site diary written on 15 March carries more weight than a witness statement written six months later recalling what happened on 15 March.

A Practical Record-Keeping Framework

Knowing what to keep is one thing. Building a system that actually works on a busy site is another. The following framework organises NEC4 record-keeping into three tiers based on frequency and purpose.

Tier 1: Daily (Non-Negotiable)

These records must be completed every working day without exception. They form the foundation of every commercial process under the contract.

  • Site diary. Narrative account of work completed, conditions encountered, instructions received, visitors, and any events that could have commercial implications. Three to five sentences per section is sufficient. Brevity with specificity beats length without substance. See the site diary guide for detailed guidance on what to include.
  • Labour allocation. Names, trades, hours worked, and the activity each person was allocated to. This is the single most important record for substantiating Defined Cost.
  • Plant and equipment. Machines on site, hours operated, and activity allocation. Include standing time if plant is idle due to a compensation event.
  • Photographs. Date-stamped and location-tagged photographs of work faces, conditions, and anything unusual. Aim for enough coverage that a commercial manager who was not on site can reconstruct what happened.

Tier 2: Weekly

  • Progress against programme. Update actual progress against the Accepted Programme. Note any activities behind programme and the reason for the delay.
  • Early warning review. Review the risk register and assess whether any new early warnings are required.
  • Commercial review. Reconcile records against open compensation events. Identify any gaps before they become irrecoverable.

Tier 3: Monthly and Event-Triggered

  • Programme submission. Revised programme showing actual progress and forecast to Completion per clause 32.
  • Payment application. Collate Defined Cost records for the assessment period.
  • Compensation event substantiation. Package records for any CE quotation in preparation, linking daily records to the specific event.

Digital vs Paper Records

Paper-based records served construction for decades, but they carry inherent risks that digital systems eliminate. The question is no longer whether to go digital but how to do it without creating a different set of problems.

CriterionPaper RecordsDigital Records
AccessibilityFiling cabinets, site offices, vehiclesSearchable, cloud-based, accessible from any device
CompletenessGaps often undetected until neededAutomated prompts flag missing entries
ContemporaneityOften completed retrospectively at week endTimestamped on creation, GPS tagged
LinkageManual cross-referencing across filesAutomatic linking between diary, allocation, and photos
Commercial extractionHours of manual review to identify CEsAI can flag potential compensation events in real time
Adjudication readinessDays to compile a bundleExport filtered records in minutes

Gather's QS AI Agent reviews site diary entries daily and flags potential compensation events that might otherwise go unnoticed. On average, Gather identifies 40% more compensation events than manual review alone, because it reads every diary entry against every clause in the contract. The result is that nothing falls through the cracks and nothing gets time barred because awareness was missed.

The shift from paper to digital does not change what records you need to keep. It changes how quickly you can assemble those records when the commercial moment arrives. The Contractor who can produce a structured CE substantiation package within 24 hours of notification has a material advantage over one who needs two weeks to find the right diary entries.

NEC4 Explained

Frequently Asked Questions

What records does NEC4 require the Contractor to keep?

NEC4 does not prescribe a single list of required records, but the contract's commercial mechanisms create obligations to maintain daily site diaries, labour allocation sheets, plant and equipment records, material delivery records, photographic evidence, weather records, progress records against the Accepted Programme, and a complete correspondence log. These records substantiate compensation event quotations, defend against disallowed cost, and support programme updates.

How do site diary records help with NEC4 compensation events?

Site diary entries establish the date of awareness for compensation events, which starts the eight-week time bar under Clause 61.3. They also provide the contemporaneous narrative that supports quotations under Clause 62.2. Daily records of labour, plant, and conditions before and after an event create the baseline comparison needed to calculate the Defined Cost impact. Without diary records, the Contractor cannot prove when awareness arose and risks the notification being time barred.

What happens if a Contractor has poor records under NEC4?

Poor records under NEC4 lead to several commercial consequences. Compensation event notifications may be time barred because the Contractor cannot prove the date of awareness. Defined Cost may be disallowed under the Disallowed Cost definition in Clause 11.2 because the Contractor cannot demonstrate the cost is justified. Quotations may be reduced because baseline and impact data is incomplete. Extensions of time may be refused because actual progress against the Accepted Programme is not documented. In adjudication, the party with better contemporaneous records almost always wins.

How long should NEC4 project records be retained?

NEC4 does not specify a retention period, but the Limitation Act 1980 provides the framework. For contracts executed under hand, the limitation period is six years from completion. For contracts executed as a deed, it is twelve years. Best practice is to retain all project records for twelve years from the date of the Defects Certificate to cover both scenarios and any latent defect claims.

Are digital site records accepted as evidence in NEC4 adjudication?

Yes. Digital records are fully accepted as evidence in NEC4 adjudication and are increasingly preferred over paper records. Digital records carry automatic timestamps, GPS location data, and audit trails that paper records cannot provide. Adjudicators particularly value the contemporaneity that timestamped digital entries demonstrate, as it removes the suspicion of retrospective completion that can undermine paper diary entries.

What is the difference between NEC4 record keeping and traditional contract record keeping?

The key difference is timing. Traditional contracts assess variations retrospectively based on actual cost, so records are assembled after the event, often at final account. NEC4 assesses compensation events prospectively from the dividing date, meaning records must be maintained contemporaneously to establish a credible baseline and forecast. NEC4 also imposes strict time bars that make real-time record keeping a commercial necessity rather than a best practice recommendation. Contractors working under NEC4 who treat records as an end-of-project activity will lose entitlement they should have recovered.

Site records, assured

Stop Losing Entitlement to Incomplete Records

Gather turns daily site records into structured NEC4 compliance data, flags potential compensation events before the time bar expires, and builds substantiation packages automatically.

40% more compensation events identified vs manual review

Deliver NEC projects better Free 20-min demo
Book demo