Key Takeaways

The dividing date separates actual from forecast

The dividing date is a fixed point that separates work done from work not done. For instructions, it's the instruction date. For notified events like weather, it's the notification date. It locks in the accepted programme at that point and stops assessments becoming a moving target as admin delays occur.

Progress the programme before assessing the CE

You must progress the accepted programme current at the dividing date to reflect actual status before modelling the compensation event. First progress, then rebaseline, then add the CE. Skipping this step burns up the contractor's internal float and loses true entitlement to extensions of time and costs.

There is no separate prolongation claim

Unlike traditional contracts with global delay claims at the end, NEC requires you to assess time impact within each compensation event quotation. Every delay must be attributed to specific events and priced progressively. If you're twelve weeks late, you need to show exactly which CEs caused it and when.

No accepted programme means no entitlement

Without an accepted programme, you're guessing. The project manager can withhold 25% of payment until you submit one. NEC requires it. Keep yours current and accepted. If you let it lapse, you have no baseline to demonstrate impact and your compensation event assessments fall apart.

Session Transcript
Download PDF
Read More
Audience Q&A

Heading 1

Heading 2

Heading 3

Heading 4

Heading 5
Heading 6

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur.

Block quote

Ordered list

  1. Item 1
  2. Item 2
  3. Item 3

Unordered list

  • Item A
  • Item B
  • Item C

Text link

Bold text

Emphasis

Superscript

Subscript

Audience Q&A

Excel / PowerBI
MCP Server
Aconex