Eleven free Excel templates covering the daily site record: diary, allocation, timesheets, deliveries, weather, meeting minutes, defects and weekly reporting. Built by quantity surveyors, no email wall.
A site record is only worth keeping if it can later be used as evidence: to support a claim, defend against one, prove progress, or account for labour and plant. A diary entry nobody can find or reconstruct at final account isn't a record, it's paperwork.
The daily record layer, from the diary itself through to the close-out trackers it feeds. Every one is a direct .xlsx download.
The daily record template every entry in this library builds on.
→A structured daily report covering labour, plant, progress and events on site.
→Daily labour and plant allocation against planned resource.
→Rolls daily allocation up into a project level output tracker.
→Track hours worked against output to see true labour productivity by gang.
→Record every delivery against order, with shortfalls and damage flagged as they happen.
→Record weather events against the contractual test for a compensation event or extension of time.
→The natural next step from the site diary template, built for weekly reporting.
→A close out checklist for handover, snagging and final account preparation.
→Decisions and actions from every meeting, with owners and due dates that carry forward until closed.
→Log every defect at handover with location, trade and close-out status.
→| Template | Core fields | Best for |
|---|---|---|
| Site diary | Date, weather, labour, plant, materials, instructions, visitors | The daily baseline record |
| Daily report | Activities, progress narrative, issues, photos reference | Client-facing daily summary |
| Allocation sheet | Trade, gang size, hours, plant, activity code | Daily resource capture |
| Allocation tracker | Planned vs actual resource by week, variance | Output and productivity review |
| Timesheet and productivity | Hours by gang, output units, productivity rate | Labour cost and efficiency tracking |
| Materials delivery log | Order ref, delivery date, quantity, shortfall, damage | Supply chain and procurement evidence |
| Weather delay log | Date, weather measured, contractual test, impact | NEC4 weather compensation events, EOT claims |
| Weekly report workbook | Rolls up daily diaries into a weekly summary automatically | Weekly client and internal reporting |
| Completion checklist | Snagging items, handover documents, final account items | Close out and handover |
| Meeting minutes and action tracker | Attendees, decisions, actions, owners, due dates | Site and progress meeting follow-up |
| Punch list and defects tracker | Location, trade, defect description, close-out status | Handover and snagging |
A filing cabinet of completed diaries isn't the same thing as a defensible commercial position. The gap between the two is retrieval: when a dispute arises or a compensation event needs substantiating, someone has to find the right entries, cross reference them against the contract, and turn a stack of forms into an argument.
Most teams find that step out on a live project, months after the events happened, when memory's faded and the person who wrote the entry has moved on. The template you keep the record in matters less than whether the record can be searched, linked to a clause, and produced on demand.
Gather turns every diary entry into a searchable, contract-linked commercial record automatically, so the evidence is ready before you need it, not scrambled together after.
See how Gather turns records into evidence A 30 minute call. No commitment. Bring one of your live diaries.Weather, labour and plant on site, materials received, progress made, instructions given, visitors, and any event that could affect cost or programme, so the record stands on its own months later.
For the life of the contract at minimum, and typically 6 to 12 years afterwards for limitation purposes under English law. Keep records accessible, not just archived.
Because the entry describes what happened but not why it matters contractually. A weather delay log that doesn't reference the contractual test for a compensation event is a record of the weather, not evidence of entitlement.
Gather reads your diaries as they come in and keeps every commercial and programme record up to date automatically.
Book a demoThe commercial registers are in Construction Commercial Management Templates, and the programme and cost view is in Construction Project Controls Templates. All 23 are listed on Free templates and tools.




Gather Insights Limited is a limited company registered in England & Wales. Registered number: 10215108.
Copyright © Gather Insights Limited 2026