A daily allocation sheet template gives you a structured format to record which operatives worked on which activities, for how many hours, on a given day. Done well, it's your primary evidence document for Defined Cost under NEC4 Options C, D, E, and F. Done badly, it's a scrap of paper that gets binned. This page gives you a ready-to-use construction allocation sheet template, explains what each field captures and why it matters, highlights the fields that are non-negotiable under NEC4, and shows you how Gather replaces the whole manual process.
The Template
Print it, copy it into Excel, or use it as the blueprint for your digital form. The structure below is tested across civil engineering, highways, rail, and utilities projects.
Section 1: Header Information
| Field | What to Record | Example |
|---|---|---|
| Project Name | Full project name as per the contract | A14 Cambridge to Huntingdon – Section 3 |
| Contract Reference | Your internal contract number | CON-2025-047 |
| NEC4 Option | The pricing mechanism in play | Option C (Target Cost) |
| Date | Full date: day, date, month, year | Monday 10 March 2025 |
| Week Number | Contract week or programme week | Week 34 |
| Supervisor / Foreman | Name of the person completing the form | J. Ahmed |
| Section / Location | The part of site the sheet covers | Section 3B – Earthworks Cut 1 |
| Weather Summary | Brief note on conditions (see site diary for full detail) | Heavy rain AM, dry PM |
Why the header matters: The contract reference and NEC4 option tell you immediately what evidential standard applies. Under Option C, every allocation sheet feeds into Defined Cost assessment. Under Option A (lump sum), the commercial weight is different. Getting this right in the header stops confusion downstream.
Section 2: Labour Allocation
This is the core of the document. Every operative, every trade, every hour. All recorded against the activity they actually worked on.
| Operative Name | Trade / Role | Employer | Start Time | Finish Time | Break (mins) | Hours Worked | Activity Code | Notes |
|---|---|---|---|---|---|---|---|---|
| T. Morrison | Excavator Operator | [Contractor] | 07:00 | 17:00 | 60 | 9.0 | E-CUT-01 | Machine breakdown 11:00-12:00 |
| K. Osei | Banksman | [Contractor] | 07:00 | 17:00 | 60 | 9.0 | E-CUT-01 | Standing time 11:00-12:00 |
| R. Patel | Groundworker | [Subcontractor: LB Civil] | 07:30 | 16:30 | 30 | 8.5 | D-PIPE-03 | |
| [Add rows as needed] | ||||||||
| Totals | 26.5 |
Column guidance:
- Operative Name: Full name. Not "operative 1". When a compensation event is assessed 18 months later, you need to be able to trace this person.
- Trade / Role: Groundworker, excavator operator, banksman, concretor, steel fixer, etc. Not just "labourer". The rate differs and so does the commercial impact.
- Employer: Whether direct, agency, or subcontractor, and which subcontractor. This determines which labour schedule rate applies under NEC4 Defined Cost.
- Start / Finish / Break: The basis for calculating hours worked. Never leave this blank and backfill a round number. It won't survive scrutiny.
- Hours Worked: Calculated from start/finish/break. Double-check the arithmetic.
- Activity Code: Links back to your work breakdown structure or programme activity. This is how you connect the allocation sheet to delay analysis. If you don't have formal activity codes, use a simple description like "Excavation Cut 1" or "Drainage Pipe Section 3".
- Notes: Any deviation from planned working. Machine breakdowns, standing time, restricted working due to utilities, instructions received. A one-line note here can save weeks of argument later.
Section 3: Plant and Equipment
| Plant Item | Registration / ID | Operator | Hired (Y/N) | Hire Company | Start | Finish | Hours | Activity Code | Notes |
|---|---|---|---|---|---|---|---|---|---|
| 20T Excavator | EX-07 | T. Morrison | N (own) | 07:00 | 17:00 | 9.0 | E-CUT-01 | Breakdown 11:00-12:00 | |
| 8T Dumper | DU-12 | Agency | Y | Plant Co. | 07:30 | 17:00 | 8.5 | E-CUT-01 | |
| Pump (submersible) | PU-04 | N/A | Y | Plant Co. | 08:00 | 17:00 | 9.0 | D-DRAIN-01 | Deployed due to groundwater |
| [Add rows] |
Column guidance:
- Registration / ID: You need a unique identifier, not just "excavator". If there are two excavators on site, you need to know which one stood idle.
- Hired (Y/N) and Hire Company: Under NEC4 Defined Cost, hired plant is included at the hire rate with a schedule-of-cost-components adjustment. Own plant uses the published schedule rates. The distinction matters for your cost records.
- Hours: Claimed plant hours must be supported by contemporaneous records. A hire company invoice alone won't do it if the Project Manager challenges whether the plant was actually working on the compensated activity.
- Notes: Record any standing time, breakdowns, or restricted use against the reason. This is your evidence if you need to claim for idle plant.
Section 4: Materials Received
| Material | Supplier | Delivery Note Ref | Quantity Received | Unit | Activity Code | Notes |
|---|---|---|---|---|---|---|
| Type 1 Sub-base | Tarmac | DN-2025-4491 | 24 | tonnes | R-BASE-02 | |
| Pre-cast manhole | Marshalls | DN-2025-4492 | 3 | units | D-MH-07 | Delivered damaged, 1 rejected |
| [Add rows] |
Note: The allocation sheet is not a full materials management system. Record what arrives on site and against which activity. Your site diary should carry the narrative detail on any materials issues (damaged goods, wrong spec, late delivery that caused a programme impact).
Section 5: Subcontractor Summary
Where multiple subcontractors are working, a one-line summary per subcontractor keeps the sheet readable without losing the overview.
| Subcontractor | Scope | Operatives on Site | Hours Worked | Supervisor | Notes |
|---|---|---|---|---|---|
| LB Civil Ltd | Drainage works – Section 3 | 4 | 34.0 | B. Singh | |
| TL Steelfix Ltd | RC frame – Block B | 6 | 51.0 | P. Nduka | Rebar delivery delayed 2 hours |
| [Add rows] |
Why this matters: On NEC4 Options C and D, subcontractor Defined Cost flows up to the main contractor's cost records. If a subcontractor causes or is affected by a compensation event, you need to be able to isolate their hours and costs. A subcontractor summary makes this straightforward.
Section 6: Authorisation
| Role | Name | Signature | Date |
|---|---|---|---|
| Foreman / Supervisor completing form | |||
| Site Manager reviewed | |||
| Project Manager / QS reviewed (if required) |
Practical note: On most sites, the foreman completes the form at end of shift and the site manager reviews the following morning. On NEC4 contracts, some clients require the Project Manager's representative to countersign. Check your contract. The requirement may be in the Works Information or the Z clauses.
Labour Allocation Sheet Template: The NEC4 Fields You Cannot Afford to Miss
Most allocation sheet templates on the internet were built for payroll, not contracts. They track hours well. They don't track Defined Cost evidence. Under NEC4 Options C, D, E, and F, your allocation sheets are a primary input to compensation event assessment. Get these fields right, or you're handing the Project Manager a reason to disallow.
The Five NEC4-Critical Fields
| Field | Why It's Non-Negotiable Under NEC4 | What Happens Without It |
|---|---|---|
| Trade / Role (not just name) | Labour schedule rates vary by trade. The Project Manager assesses CE costs using the schedule of cost components and needs the right rates | Assessment defaults to a blended rate, almost always lower than your actual cost |
| Employer (direct / agency / sub) | The Defined Cost schedule distinguishes between employed and hired labour | Disputes over which rate applies; potential disallowed cost |
| Activity Code | Links operative hours to a specific CE for assessment purposes | Impossible to isolate the cost impact of a CE when multiple activities run concurrently |
| Standing Time / Idle Time Notes | Idle plant and labour is a Defined Cost if the CE caused it | No evidence for standing time claims; Project Manager assesses nil |
| Subcontractor Identification | Subcontractor Defined Cost is included in the main contractor's CE assessment | Can't demonstrate subcontractor cost impact; CE assessed on main contractor costs only |
I've seen these fields missing on allocation sheets from Tier 1 contractors on rail packages worth over £100M. The records existed, but they weren't structured to support NEC4 assessment. The commercial team spent weeks reconstructing evidence that should have been captured daily.
What "Defined Cost" Means for Your Template
Under NEC4 Options C and D (target cost), Defined Cost is calculated using the schedule of cost components. Labour falls under People Costs. The Project Manager can disallow any cost that isn't properly evidenced. Your allocation sheet is the evidence.
Three things your template must do to survive a Defined Cost audit:
- Identify each person by name and trade (so the correct schedule rate can be applied)
- Record actual hours worked with start, finish, and break times (not rounded daily totals)
- Link hours to an activity or compensation event reference (so costs can be allocated correctly)
If your template does those three things consistently, you're in a strong position. If it doesn't, you're handing the Project Manager a reason to disallow.
How to Complete the Labour Allocation Sheet Template
End-of-Shift Completion
Complete the allocation sheet at the end of each working shift. Not the next morning. Not on Friday afternoon for the whole week. End of shift.
People forget. The machine breakdown at 11am gets forgotten by 4pm when the site is buzzing again. The subcontractor who left at lunchtime doesn't get recorded. Verbal instructions go unlogged. Memory degrades fast on a construction site, especially on complex multi-activity days.
The five-minute rule: If the sheet's been maintained through the day (quick note when something changes), end-of-shift completion takes five minutes. If it's taking 20 minutes, someone's completing it retrospectively.
Worked Example: Machine Breakdown on a Rail Package
Here's how the template works in practice. This is a fictional but realistic scenario.
Project: Midlands Rail Electrification Package, NEC4 Option C, contract value £28M.
Date: Tuesday 4 February 2025. A 20-tonne excavator (EX-07) breaks down at 10:45 and isn't repaired until 13:30.
The foreman completes the labour section at end of shift:
| Operative | Trade | Employer | Start | Finish | Break | Hours | Activity Code | Notes |
|---|---|---|---|---|---|---|---|---|
| T. Morrison | Excavator Operator | [Contractor] | 07:00 | 17:00 | 60 | 9.0 | OLE-FOUND-02 | Machine breakdown 10:45-13:30, standing time 2.75 hrs |
| K. Osei | Banksman | [Contractor] | 07:00 | 17:00 | 60 | 9.0 | OLE-FOUND-02 | Standing time 10:45-13:30 |
And in the plant section:
| Plant | ID | Hired | Start | Finish | Hours | Activity Code | Notes |
|---|---|---|---|---|---|---|---|
| 20T Excavator | EX-07 | N | 07:00 | 17:00 | 9.0 | OLE-FOUND-02 | Breakdown 10:45-13:30, idle 2.75 hrs confirmed |
Four months later, when the commercial team submits a compensation event under clause 60.1(2) for a Client-instructed design change to the foundations, the QS can demonstrate: on 4 February, the excavator was already standing idle for 2.75 hours due to breakdown. The CE instruction arrived that afternoon. The time impact is calculated from a clean baseline.
That's the difference a well-completed allocation sheet makes. Without those notes, the Project Manager's assessment starts from scratch.
Common Completion Mistakes
Recording total headcount only, not trade-by-trade. "12 operatives on site" tells you nothing useful. "3 excavator operators, 4 groundworkers, 2 concretors, 3 banksmen" tells you everything. Trade rates differ, disruption impacts differ, and the Project Manager needs the breakdown to apply the right schedule of cost component rates.
Leaving the activity code blank. It's the most common failure I see. Foremen fill in names and hours but skip the activity code because they don't know the reference off the top of their heads. Fix it by printing the current week's programme activities on the reverse of the form. Or have the QS pre-populate the codes each Monday.
Not recording standing time. If an operative was on site but not productively employed for part of the day, that goes in the notes column. "Standing time 10:00-12:00, crane unavailability" is gold if there's a crane-related CE later. "9 hours worked" with no notes is useless.
Unsigned forms. Authorisation gives the document evidential standing. An unsigned allocation sheet is just a piece of paper with numbers on it. Both the completing foreman and the reviewing site manager should sign it.
Week-in-arrears completion. Some sites complete allocation sheets weekly. Don't. Daily completion is the standard, and anything less destroys the document's credibility as contemporaneous evidence in a compensation event assessment.
Downloadable Version
A downloadable version of this template is available as a formatted Excel spreadsheet. It includes:
- Pre-formatted tables for labour, plant, materials, and subcontractors
- A dropdown list for common trades and roles
- Auto-calculation for total hours
- A notes and activity codes reference sheet
To get the downloadable template, request it via the Gather website. We'll send it to you free.
How Gather Replaces This Template
Manual allocation sheets work. They're also slow, inconsistent between foremen, and disconnected from your commercial records. Gather is the digital replacement.
What Gather does differently:
- Site engineers and foremen complete allocation data on a mobile app, at end of shift, on site
- Operative names and trades are selected from a pre-populated list (no free-text errors)
- Every entry is time-stamped and GPS-tagged (no retrospective completion)
- Allocation data is linked directly to the programme and compensation event register
- The QS can review allocation records in real time, not at month-end
- NEC4 Defined Cost reports are generated automatically from the allocation data
On a £40M highways package using Gather, the commercial team recovered £1.2M in previously unrecognised compensation event costs across 14 months. The records were always there. They just weren't structured in a way that supported NEC4 assessment until Gather was in place.
For more on how AI is changing site record management, see our guide on how site diary data supports compensation event detection.
.webp)




