Daily Diary to Weekly Report Workbook: Free Excel Template

A ready to use Excel workbook that takes raw daily site diary notes and turns them into a management ready weekly report, without retyping a single entry. The natural next step after keeping the diary itself. Built by quantity surveyors.

A daily diary to weekly report workbook is a linked Excel file that takes raw daily site notes on one tab and rolls them into a summarised weekly management report on another, without manual re-entry. It exists to close the gap between what the site records and what management actually reads.

Most projects lose this link entirely: the diary is kept on site, the report is written separately in the office, and the two drift apart within a fortnight.

What a good workbook covers

Most site teams keep a diary on site and write a report in the office, and the two are built by different people at different times from different memories. The workbook fixes this by making the report tab a formula driven summary of the diary tab, so the report cannot say anything the diary did not.

FieldWhy it matters
Daily diary input tab (date, weather, labour, plant, events)The single place raw site information gets entered, once, by whoever is on site
Weekly summary tab (auto-linked)Rolls the week's diary entries into headline numbers and a narrative, with no retyping
Key events and instructions flaggedSurfaces anything from the week that a QS or PM needs to see, not buried in daily notes
Weather and delay logRolls into the report automatically, ready to support a time extension if one is needed later
Sign off rowRecords who reviewed the week's diary before the report went out

How to turn daily site diary notes into a weekly report

Five steps, run once a week. The point of the workbook is that most of them happen automatically once the diary tab is filled in as the week goes along, rather than being reconstructed on a Friday afternoon.

  1. Log each day in the diary tab

    Record date, weather, labour, plant and events on the daily diary input tab as they happen.

  2. Let the summary tab roll up automatically

    The weekly report tab reads the diary tab's rows for the reporting week, with no manual retyping.

  3. Flag commercially significant events

    Mark any entry that could be a delay, instruction or compensation event so it carries through to the report narrative.

  4. Review and sign off

    Have the site manager or QS review the week's diary before the report is issued.

  5. Issue the weekly report

    Send the completed weekly summary tab to the client and project team.

The template, field by field

DateNote / eventLabourPlantWeather
21 JulLate delivery, precast units182Dry
22 JulSite closed, high winds00Storm
23 JulCladding gang mobilised223Dry

Scroll the table sideways to see every column.

The report tab pulls straight from these rows: no separate typing, no separate memory of what happened on site that week.

Download the free template

The Excel workbook with a daily diary input tab, an auto-linked weekly report tab, and a weather and delay log built in.

Download the free template (.xlsx) Free download. No email needed. Yours to use and share with your team.

When the spreadsheet is not enough

The workbook rolls the week. The site diary is the daily input the commercial manager actually trusts. The QS AI Agent reads those entries before the weekly goes out, so the one row that is a compensation event is not sitting quietly in the diary tab. Start from the site diary template and roll it with the progress report template.

Frequently asked questions

What is the difference between a diary and a weekly report?

The diary is the raw daily record: what happened on site, who was there, what the weather did. The weekly report is a summary written for management and the client, pulling the week's diary entries into headline numbers and a narrative.

How do I turn a daily diary into a weekly report?

Link the two in one workbook so the report tab reads directly from the diary tab's rows for that week, rather than being typed up separately. This removes the retyping step and the drift between what was recorded and what gets reported.

Is this the same as the site diary template?

No. Our site diary template is the daily input record. This workbook is the next step: it takes that daily input and rolls it into a weekly report automatically, in the same file.

Who should review the diary before the report goes out?

Whoever is commercially accountable for the week, usually the site manager or a QS, should sign off the diary entries before the weekly report is issued, so any commercially significant event is caught before it reaches the client.

When the spreadsheet is no longer enough

The workbook rolls the week only if the daily rows are true. Capture the day on the site diary, and let the QS AI Agent flag commercially significant events before the weekly goes to the client.