NEC4: Scope - What It Is and What It Isn't

Edition 13 of the NEC4 webinar series takes on the Scope: the document that says what the Contractor has to deliver and the limits on how it does it. Glenn Hide (GMH Planning) and Ben Walker (Gather) write a complete Scope for a Sunday roast for six, and use it to show where each statement belongs, why every requirement needs an objective test, and how a constraint or a prescribed method quietly hands risk back to the Client. David Allen of CECA Southern opens with what members keep reporting: too many Scopes are cut and pasted from the last project.

Presented By
Glenn Hide
Glenn Hide
GMH Planning
Ben Walker
Ben Walker
Gather
Key Takeaways

The Scope says what, and only limits the how

The method belongs to the Contractor by default, and the Client observes it through the programme. Prescribe a method only when you can say why (a nuclear safety case, a rail possession, a live water asset), because if the Contractor follows your recipe to the letter and the Yorkshire puddings still don't reach 60mm, that gap is the Client's.

If you can't write the pass column, you haven't specified the works

"Nice and pink" is an opinion. 52 to 55 degrees at the core after resting is a requirement. The testing clauses only apply to tests the Scope or the law requires (clause 41.1), so write section 700 alongside section 100: what is tested, what counts as a pass, who does it and when.

Dates live in Contract Data, not in the Scope

Completion Dates, Key Dates and the starting date belong in Contract Data, while the Scope says what done looks like for each section. Put a date in both and sooner or later they'll disagree. An objective statement of Completion stops the certificate being held up and avoids Defects being corrected after Completion, which is Disallowed Cost under Options C, D, E and F.

Every change to the Scope has a price, and some have a hidden one

Adding a constraint after the Contract Date, asking for a bigger gratin dish or telling the cook to skip a test are all changes to the Scope, and usually compensation events under 60.1(1). The exceptions are a change the Contractor asks for to its own design and a change to accept a Defect. Withholding acceptance of a design for a reason the contract doesn't give is allowed under clause 13.8, but it's a compensation event under 60.1(9).

Further Reading

GMH Planning's own guidance notes and CECA bulletins on this topic. They explain the standard provisions and are useful alongside, not instead of, the executed contract.

Check the contract form, edition, incorporated amendments, main and secondary options, Contract Data and any Z clauses for your own project.