Key Takeaways

An early warning does not stop the clause 61.3 clock

Notifying an early warning is not the same as notifying a compensation event, and it does not stop the eight-week period in clause 61.3 from running. If the risk turns into a compensation event, notify it separately, and check your Z clauses in case the period has been amended. You also don't need an early warning before you can notify a compensation event.

Withholding acceptance of the programme does not buy the Project Manager time

Under clause 64.1, if the Project Manager has not accepted the Contractor's latest programme for a reason stated in the contract, the Project Manager assesses the compensation event. Acceptance does not change the Contractor's responsibility to Provide the Works (clause 14.1), so check the programme properly, but don't hunt for a technicality to hold it back.

Deleted work needs a double assessment under clause 63.1

The change to the Prices is the event's effect on Defined Cost plus the resulting Fee, so price what the deleted work would have cost in Defined Cost and compare it with what it costs now. In Ben's worked example, an Activity Schedule item priced at £250,000 would have cost £160,000 and now costs £10,000, giving a reduction of £150,000 plus 10% Fee: £165,000 off the Prices, not £239,000.

Assumptions are stated by the Project Manager, not slipped into a quotation

Clause 61.6 requires the Project Manager to state assumptions where the effects of a compensation event are too uncertain to be forecast reasonably, and if an assumption later proves wrong, that is a compensation event under 60.1(17). Glenn's point is that nothing in the ECC turns a Contractor's own assumption into a Project Manager's assumption because the quotation was accepted. If the Project Manager isn't forthcoming, the Contractor can suggest assumptions for the Project Manager to state in writing; otherwise the risk has to be priced.

Further Reading

GMH Planning's own guidance notes and CECA bulletins on this topic. They explain the standard provisions and are useful alongside, not instead of, the executed contract.

Check the contract form, edition, incorporated amendments, main and secondary options, Contract Data and any Z clauses for your own project.

Session Transcript
Read More

Audience Q&A