Lookahead Planner Template: Free 2, 4 and 6 Week Excel Programme

A ready to use Excel lookahead for site teams, with a 2, 4 or 6 week view, constraints and predecessor tracking built in. Built by quantity surveyors.

WD
Will DoyleFounder and CEO, Gather · Chartered QS · Last reviewed 22 July 2026

A lookahead planner is a short interval programme, usually 2, 4 or 6 weeks, that a site team uses to sequence upcoming activities, flag constraints and check resources before work starts. It sits below the master programme and above the daily allocation, and it is reissued every week.

The lookahead is the document a foreman actually works from. The master programme tells the client the story. The lookahead tells the gang what happens on Tuesday.

What a good lookahead covers

A lookahead is only worth the paper it's printed on if the constraints column stays live. In practice it gets filled in once, then the plan quietly drifts from what the diary records actually happening. This template starts every week from last week's actual progress rather than last week's plan, so the drift shows up while you can still do something about it.

FieldWhy it matters
Activity and locationTies the plan to a physical area so clashes show up before they happen on site
Predecessor and durationKeeps the sequence logic visible instead of buried in someone's head
Constraint (design, materials, access, resource)Forces the team to name what could stop the activity, not just when it should start
Status (on track, at risk, slipped)Colour coded so a project manager can scan the week in seconds
Week view toggle (2/4/6 week)Same data, three horizons: this week's detail, this month's sequencing, this quarter's shape

The template, field by field

RefActivity / locationStartStatusConstraint
LA-041Formwork, Pier 4 (west face)28 JulOn trackNone
LA-042Steel fix, deck bay 330 JulAt riskMaterials
LA-043Pour, Pier 401 AugPlannedAccess

Each row carries a constraints note and a colour coded status so the site manager can flag anything that needs chasing before Monday's meeting, not during it.

Download the free template

The Excel file with 2, 4 and 6 week toggle views, constraint tracking and a worked example tab. No form to fill in.

Free download. No email needed. Yours to use and share with your team.

How Gather automates this

A lookahead is only as good as the actual progress it is built from. If this week's diary entries have not been logged when Monday's plan gets written, the lookahead starts from a guess, not a fact.

If reconstructing what happened on site is costing your commercial team days every month, there is a faster way.

Gather's AI QS turns the daily record into a contract aligned commercial position automatically, so the claim writes itself from evidence instead of memory.

See the AI QS in action A 30 minute call. No commitment. See if it fits how your team already works.

FAQ

Frequently asked questions

What is the difference between a lookahead and a master programme?▾

The master programme sets out the whole project sequence and milestones. The lookahead is a short interval slice of it, usually 2 to 6 weeks, reissued weekly with the level of detail (location, constraint, resource) the master programme does not carry.

How often should a lookahead be updated?▾

Weekly, at minimum, against actual progress. A lookahead that is not reissued against what actually happened on site drifts within two or three weeks.

What is a constraint in a lookahead planner?▾

Anything that could stop an activity starting on time: outstanding design information, materials not yet on site, access not yet granted, or a resource not yet allocated. Naming the constraint early is what makes the lookahead useful rather than decorative.

Is a 2, 4 or 6 week lookahead better?▾

They serve different meetings. 2 week for the daily site briefing, 4 week for the project manager's weekly review, 6 week for procurement and subcontractor coordination. This template gives you all three from one data set.

Stop planning from a guess

Gather reads your site diaries as they come in, so next week's lookahead starts from what actually happened.

Book a demo
A six-week lookahead is a procurement tool, not a wall chart.

Rebuild it from last week's diary, not last week's plan. Plan holds that lookahead against the live programme so constraints (design, materials, access) show up before the gang is standing.

See Plan against a live programmeA 30 minute call. Bring next week's lookahead if you have it.