Construction Project Dashboard Template: Free Excel Weekly Reporting Sheet

A ready to use Excel dashboard for the weekly project meeting: programme status, cost, open RFIs, variations, delay days and safety on one page. Built by quantity surveyors.

WD
Will DoyleFounder and CEO, Gather · Chartered QS · Last reviewed 23 July 2026

A construction project dashboard is the single page summary of a project's programme, cost and risk status, built from weekly metrics so the project team can see planned versus actual progress, cost to complete, open RFIs and variations, delay days, safety observations and overdue actions without opening five other spreadsheets.

Most contractors build one every week for the client, the board, or both. The problem is rarely the layout. It is that every number on it has to be typed in by hand from somewhere else.

What a good project dashboard covers

Friday afternoon, someone re-keys numbers that already exist in four other places. That's why the dashboard is only ever as accurate as the last person who copied them across. This template won't fix the re-keying on its own, but it gives you one clean weekly input row and a dashboard that recalculates the moment that row is filled in, so it only happens once.

FieldWhy it matters
Planned % and Actual %The two numbers every progress conversation starts from
BAC, Actual cost, Earned valueEnough to see cost and schedule performance at a glance, without a full EVM workbook
Open RFIs and open variationsFlags design and commercial risk building up before it shows in the cost line
Delay daysTracks cumulative delay week on week, not just this week's excuse
Safety observationsKeeps safety on the same page as commercial status, where it belongs
Overdue actionsPulls straight from the Issues & Actions tab so nothing gets dropped between meetings

The template, field by field

Week endingPlanned %Actual %Open RFIsOpen var.Delay daysOverdue
28 Feb12%12%8014
28 Mar24%24%7123
28 Apr36%36%6102

The Project Data tab is the only place anyone types anything. The Dashboard tab reads it and shows latest planned, latest actual, progress variance, open RFIs and overdue actions as four cards. The How to use tab explains the whole flow with a worked example.

Download the free template

The Excel file with a weekly project data tab, an automatic dashboard, and an Issues & Actions tracker.

Download the template (.xlsx) Free download. No email needed. Yours to use and share with your team.

Worked example: three weeks of project data

Over three weekly entries the project data tab shows a £3.5m job holding to plan: 12%, 24% and then 36% actual against the same planned figures, earned value tracking cost almost exactly. Open RFIs fall from 8 to 6 as the design team clears the backlog, one variation opens in week two and stays open, and delay days spike to 2 in week two before clearing. None of that took a formula to explain. It took someone reading three rows of a table, which is the whole point of a dashboard: turn data into a five second read for the person running the meeting.

Now picture the same project on a bad week: the person who normally updates the sheet is on leave, so Friday's dashboard either goes out with last week's numbers relabelled, or it does not go out at all. Either way, the meeting runs on stale information and nobody in the room knows it.

How Gather automates this

A dashboard is a summary. It cannot be more accurate than the records it summarises, and on most projects those records live in diaries, allocations, instructions and correspondence that nobody has rolled up into a weekly figure yet. The dashboard is downstream of that work, not a replacement for it.

Gather feeds this automatically from your site records, not from a Friday afternoon spreadsheet session.

Gather's AI QS turns the daily record into a contract aligned commercial position automatically, so the claim writes itself from evidence instead of memory.

See the AI QS in action A 30 minute call. No commitment. See if it fits how your team already works.

FAQ

Frequently asked questions

What should a construction project dashboard include?▾

At minimum: planned versus actual progress, budget at completion, actual cost and earned value, open RFIs and variations, cumulative delay days, safety observations and overdue actions. This template covers all of them on one weekly input row.

How often should a project dashboard be updated?▾

Weekly, in line with the project team meeting it usually feeds. A dashboard updated less often stops reflecting what is actually happening on site within a couple of weeks.

Is a spreadsheet dashboard enough for a live project?▾

It works well for one person keeping one project current. What it cannot do is populate itself from the diaries, allocations and correspondence that actually generate the numbers, which is where the manual re-keying, and the risk of a stale dashboard, comes from.

Can I use this template for a client-facing report as well as internal review?▾

Yes. The Dashboard tab is built to be screenshotted or shared as-is for a client update, while the Project Data and Issues & Actions tabs stay as the internal working detail behind it.