Commercial

Turnstiles and allocation records under NEC4

William Doyle
William Doyle
CEO at Gather
3 min read
March 13, 2026
Turnstiles and allocation records under NEC4

What you need to know

  • Attendance and deployment answer different questions.
  • No single record proves every element of Defined Cost.
  • Consider the full Disallowed cost wording and Scope requirements.
  • A record is not automatically a contractual notice.

An access log can show when someone entered or left a site. It does not necessarily show what they did while there. An allocation record can explain activity, location, deployment and standing time. Together they can help a reviewer understand people costs.

Understand each record’s limits

A swipe is evidence of an access transaction, not conclusive proof of the hours worked or their contractual recoverability. Missing or duplicated swipes, off-site duties, breaks and different entrances may need explanation. Allocation records also need checking against the facts.

Turnstiles may support a site’s access-control and emergency arrangements, but do not present physical turnstiles as universally required by CDM or as a prescribed method of CIS tax compliance. Choose controls that meet the actual legal and project requirements.

Apply the NEC4 cost rules

For NEC4 ECC Options C–E, assess people costs using the applicable cost components and Disallowed cost definition. Clause 11.2(26) includes costs not justified by accounts and records. Resource-use exclusions require their full wording, including reasonable availability and utilisation, to be considered.

Attendance alone may leave questions unanswered. That does not make a particular allocation-sheet template universally mandatory or mean that standing time is always excluded. The Scope can specify additional records, and the relevant evidence may include timesheets, payroll, agency arrangements, allocation records and site reports.

Reconcile before drawing a conclusion

If an allocation shows eight hours but an access log shows six, investigate the discrepancy. It may be an error, an off-site activity or another explainable difference. Neither record automatically overrides the other.

If a gang stood awaiting access, record the timing, cause, resources and any mitigation or redeployment. These facts can support review of a possible compensation event. They do not establish the event without applying the relevant clause and notification procedure.

Keep contractual actions separate

The standard ECC eight-week time bar runs from awareness that an event happened, subject to the exception for events the Project Manager should have notified. An allocation entry is not automatically a notification. Check amendments, authority and the required communication method.

For cost and time assessment, distinguish actual evidence from forecasts at the dividing date and demonstrate the programme effect where required. A record of four idle hours does not by itself establish four hours of delay to planned Completion.

Make recording practical

  • Use consistent person, activity and location references.
  • Capture standing time honestly and explain its cause.
  • Reconcile attendance, allocation and payroll information.
  • Retain originals and identify corrections.
  • Give the reviewer access to the supporting evidence required by the contract.

Good records make a review easier. They cannot guarantee payment, an accepted quotation or a dispute-free final assessment.

Further reading

Check the contract form, edition, amendments, options, Contract Data and Scope used on your project.

Gather helps organise site records for review. Explore Gather’s site records.

‍

Share

Keep reading

Variation Order Management: How NEC4 Clause 60 Benefits from Gather's New Variance Categorisation Feature
Commercial
July 4, 2024
4 min read

Variation Order Management: How NEC4 Clause 60 Benefits from Gather's New Variance Categorisation Feature

Compensation event vs variation. NEC4 clause 60 lists the events. A diary that says "extra work" does not tell a QS which one it is.

Read Blog
Costed Site Diaries: The Key to Accurate CVRs
Commercial
December 16, 2025
8 min read

Costed Site Diaries: The Key to Accurate CVRs

Costed site diaries and an accurate CVR. Hours, output and the activity, that day. Guess any of them and the monthly number is theatre.

Read Blog
How to Maintain a Construction Site Diary
Record Management
May 21, 2025
4 min read

How to Maintain a Construction Site Diary

A construction site diary is the daily record of what happened on site. What to write, who should write it, and why a reconstructed week will not stand up when a claim is challenged.

Read Blog
See Gather on your project

Keep site records, photos and resource allocations together for your commercial team.

Book a demo