Site Diary

Daily Allocation Sheets in Construction: What They Are and Why They Matter

A daily allocation sheet is a structured record showing exactly which labour, plant, and materials were deployed against specific activities on a construction site each day. It's the document that answers the question every commercial manager dreads: "Can you prove who was doing what, where, and for how long?" If your site diary captures the narrative of what happened on site, your allocation sheet captures the numbers behind it.

Will Doyle

Will Doyle

March 2026 · 14 min read

Most contractors have allocation sheets. Far fewer have good ones. And the gap between "we do them" and "we do them properly" is where hundreds of thousands of pounds disappear on every major project. This page explains what a daily allocation sheet actually is, why it exists, how it connects to your commercial management under NEC4, and what goes wrong when it's done badly. If you're looking for a ready-to-use template, head to our allocation sheet template page.

What Is a Daily Allocation Sheet?

A daily allocation sheet records the deployment of resources against activities for a single day. Think of it as the financial X-ray of your site operations. While a site diary tells you what happened, an allocation sheet tells you what it cost.

The typical allocation sheet captures five categories of information:

  • Labour: Names or trade categories, hours worked, and the activity each person was allocated to
  • Plant and equipment: What machinery was on site, whether it was working or standing, and which activity it supported
  • Materials: What was delivered, what was used, and against which activity reference
  • Activity references: Each resource entry ties back to a specific activity in the programme or bill of quantities
  • Subcontractor resources: The same breakdown for any subcontracted labour or plant

That last point is the one people miss. Your subcontractors' allocation records matter just as much as your own, because under NEC4 Option C contracts, their costs feed directly into your Defined Cost.

For a deeper look at the differences, see our comparison of site diaries versus allocation sheets.

Why Daily Allocation Sheets Matter Commercially

I'll be blunt. Allocation sheets aren't exciting. Nobody wakes up excited to fill one in. But they're the single most important document for protecting your commercial position on any NEC4 contract, and here's why.

Labour and Plant Are Your Biggest Cost Exposure

On a typical infrastructure project, labour and plant account for 40% to 55% of total project costs. On a £50M highways scheme, that's £20M to £27.5M spent over the project lifecycle, often with no granular record of where it went. Are your allocation sheets capturing it? Because if they're not, you're flying blind on your biggest cost line.

Without daily allocation records, your cost reporting relies on payroll data (which tells you who got paid, not what they did) and plant hire invoices (which tell you what was on site, not whether it was productive). Try building a disruption claim on that. You can't.

Defined Cost Under NEC4 Demands Granular Records

Under NEC4 Option C and Option E contracts, the Contractor is paid Defined Cost plus Fee. Defined Cost is defined in the Schedule of Cost Components, and it requires you to demonstrate that costs were actually and reasonably incurred. The Project Manager can disallow any cost that isn't supported by proper records.

Here's where it gets painful. Clause 52.2 requires the Contractor to keep records that the Project Manager can inspect. If you can't link a cost back to a specific activity on a specific day, the Project Manager has grounds to treat it as disallowed cost. I've seen this happen on a £35M rail package where the Contractor lost £420,000 in otherwise legitimate costs because the allocation sheets were inconsistent. The costs were real. The records didn't prove it.

Compensation Event Assessment Depends on Resource Records

When a compensation event occurs under NEC4, the assessment under clause 63 is based on the effect on Defined Cost. That means you need to show what resources were planned for the activity, what resources were actually used following the compensation event, and the difference between the two.

Without allocation sheets, you can't do this. You can write a compelling narrative about why the CE caused disruption, but you can't put a number on it. And in adjudication, numbers win. Narratives don't.

Proving Disruption Requires a Baseline

Disruption claims require you to demonstrate the difference between planned productivity and actual productivity. Your planned productivity comes from the Accepted Programme and your tender build-up. Your actual productivity comes from your allocation sheets.

On a £40M Network Rail electrification package in the West Midlands, the commercial team needed to demonstrate that a series of late design changes had caused a 35% drop in productivity for overhead line equipment installation. They could only prove it because they had 14 months of daily allocation sheets showing labour hours per unit of OLE installed. Without those sheets, the disruption claim, worth £1.8M, would have been guesswork.

Who Fills In a Daily Allocation Sheet?

This varies by contractor, and the variation is part of the problem.

On well-run projects, the allocation sheet is completed by the site foreman or section engineer at the end of each shift. They're closest to the work. They know which operatives were on which activity, whether the 360 excavator was productive or standing idle waiting for a permit, and how many m³ of Type 1 were laid.

On less well-run projects? It's done retrospectively by a QS or administrator using payroll records and best guesses. Sometimes days later. Sometimes weeks later. At that point, you don't have an allocation sheet. You have historical fiction.

The golden rule: the person who saw the work should record the work. If the foreman was standing at the muck-away point watching six wagons queue for two hours because the haul road was blocked by a utility diversion, that needs recording at the time. Not reconstructed from memory the following Tuesday.

For practical tips on how to capture this information effectively, see our guide on how to write a site diary.

How Allocation Sheets Fit Into the Wider Records Ecosystem

An allocation sheet doesn't exist in isolation. It's one piece of a records architecture that, when it works properly, gives you an airtight commercial position. When one piece is missing, the whole thing weakens.

Record Type What It Captures How It Links to the Allocation Sheet
Site diary Narrative of daily events, weather, visitors, instructions Allocation sheet provides the numbers behind the diary narrative
Accepted Programme Planned activities, durations, resources Allocation sheet shows actual vs planned resource deployment
Daywork sheets Agreed additional work outside the contract scope Allocation sheet provides the contemporaneous evidence for daywork claims
Cost reports Monthly cost vs budget by activity Allocation sheets feed the actual cost data into cost reports
Timesheets / payroll Who was paid for what hours Allocation sheet adds the dimension of what they were doing
Progress records Percentage complete by activity Allocation sheets link resource input to measured output

The most common failure I see? Contractors who keep site diaries and timesheets but don't connect them through an allocation sheet. The diary says "8 operatives on drainage." Payroll confirms 8 people were on site. But nobody recorded which drainage activity each operative worked on, what plant they used, or how much pipe was installed. When you need to evidence a disruption claim nine months later, you've got two documents that confirm the same vague fact and nothing that proves the detail.

Worked Example: How a Complete Allocation Sheet Protects Your Position

Scenario: On a £28M NEC4 Option C highway improvement scheme in South Yorkshire, the Client issues a revised traffic management drawing on 12 June 2025 that requires the Contractor to work from one lane instead of two for a 300m section. The Contractor notifies a compensation event under clause 61.3 on 14 June 2025.

Without allocation sheets: The Contractor knows the change slowed them down. The foreman mentions it took "about twice as long" to complete the surfacing. The QS estimates an additional cost of £85,000 based on gut feel and a rough calculation. The Project Manager assesses the CE at £40,000 because there's no evidence to support the higher figure. The Contractor accepts the assessment because they can't prove otherwise.

With allocation sheets: The allocation sheets show that for the 10 working days before the change (28 May to 11 June 2025), the surfacing gang of 12 operatives and 3 plant items completed an average of 45m of surfacing per day. For the 15 working days after the change (12 June to 2 July 2025), the same gang with the same plant completed an average of 22m per day. Material deliveries were delayed by an average of 40 minutes per load due to the restricted access.

The QS builds a Defined Cost assessment:

  • Additional labour: 12 operatives x 5 extra days x £380/day = £22,800
  • Additional plant: 3 items x 5 extra days x £1,200/day = £18,000
  • Standing time (material delivery delays): 15 days x 40 mins x £95/hr = £9,500
  • Preliminaries extension: 5 days x £4,800/day = £24,000
  • Subcontractor traffic management: 5 extra days x £3,400/day = £17,000
  • Total Defined Cost impact: £91,300 (plus Fee)

The Project Manager's assessment comes back at £86,500. Close to the Contractor's figure, because both parties are working from the same factual base. No adjudication needed.

That's the difference. Not theory. Real money, recoverable because someone filled in an allocation sheet properly every day for six weeks.

What to Include in a Daily Allocation Sheet

Your allocation sheet needs to capture enough detail that someone who wasn't on site could reconstruct what happened, what it cost, and why. Here's what good looks like.

Essential Fields

Field What to Record Example
Date and shift Day, date, shift start and end Monday 12 June 2025, 07:00-17:30
Weather Conditions that affected work Heavy rain 07:00-09:30, dry thereafter
Labour by activity Trade, number, hours, activity ref 4 x Steel fixers, 8 hrs, Act 4.3.2 (pile caps)
Plant by activity Item, hours, working/standing, activity ref CAT 320 excavator, 10 hrs (8 working, 2 standing - no permit), Act 2.1.1
Materials by activity Type, quantity, activity ref Ready-mix concrete C40, 24 m³, Act 4.3.2
Subcontractors Company, trade, number, hours, activity ref ABC Piling Ltd, 6 operatives + CFA rig, 10 hrs, Act 3.1.1
Standing time Resource, duration, reason 360 excavator stood 2 hrs awaiting statutory utility location
Instructions received Who gave it, what it was, time PM's delegate verbal instruction at 11:15 to relocate stockpile
Signatures Completed by, verified by Completed: J. Thompson (Foreman). Verified: S. Patel (Section Eng.)

For a comprehensive checklist of what to include in a site diary, see our field-by-field reference guide.

The Activity Reference Is Non-Negotiable

Every resource entry must tie to an activity reference from the programme or bill of quantities. "4 labourers on general duties" is useless for cost allocation. "4 labourers, 8 hours each, Activity 5.2.1 (concrete blinding to foundations)" tells you exactly where the cost sits.

Without activity references, your allocation sheet is just an expensive attendance register.

Common Mistakes with Daily Allocation Sheets

1. Retrospective Completion

The most damaging mistake. When allocation sheets are filled in days or weeks after the event, accuracy plummets. I've reviewed projects where the same allocation sheet was clearly copied from the previous day with minor tweaks. Under cross-examination in adjudication, this destroys credibility.

Fill them in at the end of each shift. Not the next morning. Not Friday afternoon for the whole week.

2. Missing Activity References

Recording that 8 operatives worked 10 hours is meaningless without knowing which activity consumed those hours. You might as well not bother. It's like recording that you spent money without noting what you bought.

3. Not Recording Standing Time

Standing time is cost without output. If your 360 excavator stood idle for 3 hours because the utility company didn't show up for a cable location, that's a potential compensation event. But only if you recorded it, when it happened, and why.

The natural instinct is to record productive work. You need to fight that instinct and record the gaps with equal discipline.

4. Ignoring Subcontractor Resources

Your subcontractor's allocation records are your responsibility under NEC4 Option C. Their Defined Cost feeds into your Defined Cost. If their records are poor, your commercial position is weakened even though you didn't do anything wrong.

Require your subcontractors to submit daily allocation sheets in the same format as your own. Review them weekly. Push back on vague entries immediately, not three months later during an interim application.

5. No Connection to the Programme

An allocation sheet that doesn't reference the programme is a standalone document. It tells you what resources were deployed, but not whether that deployment was efficient, on track, or disrupted. The programme is the baseline. Without it, you're recording facts in a vacuum.

6. Paper-Based Systems with No Backup

Duplicate pads in the foreman's van. Filed in a box in the site office. Then the site office gets broken into, or the van gets stolen, or someone accidentally throws the box away during a site clearance. I've seen all three.

Digital systems don't solve the discipline problem, but they do solve the storage and retrieval problem. Gather automates the connection between site diary entries and allocation data, so the commercial team can pull resource records by activity, by date range, or by cost centre without rummaging through filing cabinets.

Daily Allocation Sheet vs Site Diary: Understanding the Difference

People conflate these two documents constantly. They're related but different.

Aspect Site Diary Daily Allocation Sheet
Purpose Narrative record of daily events Quantitative record of resource deployment
Who writes it Site manager or engineer Foreman or section engineer
Content focus What happened and why Who/what was deployed where and for how long
Format Prose with structured fields Tabular, activity-referenced
Commercial use Evidence for events, instructions, conditions Evidence for cost, productivity, disruption
NEC4 relevance Supports notification of compensation events Supports Defined Cost assessment

Think of it this way: the site diary is the witness statement, and the allocation sheet is the financial evidence. You need both. For a deeper comparison, see our dedicated page on site diary vs allocation sheet.

NEC4 Context: Why the Contract Demands These Records

NEC4 doesn't use the phrase "allocation sheet" anywhere in the contract. But the contract mechanisms assume you have this level of record. Here's how.

Schedule of Cost Components

Under NEC4 Options C, D, and E, the Contractor is paid Defined Cost. The Schedule of Cost Components breaks Defined Cost into people, equipment, plant and materials, charges, and manufacture and fabrication. To claim any of these, you need to demonstrate that the cost was incurred on the project, for the project, and can be allocated to a specific activity.

That's an allocation sheet. The contract just doesn't call it one.

Clause 52: Records and Auditing

Clause 52.2 requires the Contractor to keep the records the contract requires and allow the Project Manager to inspect them. On target cost contracts, the Project Manager routinely requests to see daily resource records as part of cost audits. If you can't produce them, you're inviting the Project Manager to assess your Defined Cost at a lower figure.

Compensation Event Assessment (Clause 63)

When assessing a compensation event, clause 63.1 requires the assessment to be based on the effect on Defined Cost plus the resulting Fee. To calculate the effect on Defined Cost, you need to compare the resources that would have been needed without the compensation event against the resources actually used. Your allocation sheets provide the "actually used" side of that equation.

Disallowed Cost (Clause 11.2(26))

Defined Cost that the Project Manager decides is not justified by the Contractor's records can be classified as disallowed cost. This is the nuclear option, and it happens more often than contractors like to admit. Strong allocation records are your shield.

For more on this risk, see our guide on NEC4 disallowed cost and the bridge page on site diary compensation events.

How Gather Automates Allocation Tracking

The discipline of filling in allocation sheets will never go away. Someone on site needs to record what happened. But the downstream processes? Linking allocation data to activities. Feeding it into cost reports. Retrieving records for CE assessments. None of that needs to be manual.

Gather's QS AI Agent connects daily site records directly to your programme activities and contract mechanisms. When your foreman records labour and plant deployment through Gather's site diary, the system automatically:

  • Tags resources against programme activities
  • Flags standing time and potential compensation events
  • Links resource data to Defined Cost categories
  • Makes allocation records searchable by date, activity, cost centre, or resource type
  • Alerts the commercial team when recorded deployment differs significantly from planned deployment

The result? Your commercial team spends time on commercial management, not on chasing foremen for missing allocation sheets or reconciling paper records against payroll.

Site Diary Explained

Frequently Asked Questions

What is a daily allocation sheet in construction?

A daily allocation sheet is a tabular record showing which labour, plant, and materials were deployed against specific construction activities on a given day. It captures the quantitative "who did what, where, and for how long" data that sits behind the narrative in a site diary. Under NEC4 target cost contracts, allocation sheets provide the evidence needed to substantiate Defined Cost and support compensation event assessments.

What is the difference between a site diary and an allocation sheet?

A site diary is a narrative record of daily events, conditions, instructions, and observations. An allocation sheet is a quantitative record of resource deployment against specific activities. The diary tells you what happened. The allocation sheet tells you what it cost. Both are essential for commercial management under NEC4. For a full comparison, see our site diary vs allocation sheet guide.

Who should fill in a daily allocation sheet?

The person closest to the work, typically the site foreman or section engineer. They know which operatives worked on which activities, how long plant was productive versus standing, and what materials were consumed. Allocation sheets completed retrospectively by office-based staff using payroll data are significantly less accurate and less credible in dispute proceedings.

How does a daily allocation sheet support NEC4 compensation events?

Under clause 63.1, compensation events are assessed based on the effect on Defined Cost. This requires comparing planned resources against actual resources deployed following the event. Daily allocation sheets provide the contemporaneous record of actual resource deployment, which forms the factual basis for the Defined Cost assessment. Without them, the Project Manager may assess the compensation event at a lower value, and you'll lack the evidence to challenge that assessment.

What happens if you don't keep daily allocation sheets?

Three things. First, your Defined Cost claims become harder to substantiate, and the Project Manager may classify unsupported costs as disallowed cost under clause 11.2(26). Second, your compensation event quotations lack the factual basis to support your assessed figure, leading to lower settlements. Third, in adjudication or dispute proceedings, the absence of contemporaneous records weakens your credibility and shifts the evidential burden against you. On a £50M project, poor allocation records can easily result in £500,000 to £1M of unrecoverable costs over the project lifecycle.

Can digital tools replace paper allocation sheets?

Digital tools don't replace the discipline of recording what happened on site. Someone still needs to capture the information at the point of work. What digital tools like Gather do is eliminate the downstream problems: lost paperwork, illegible handwriting, data that can't be searched or analysed, and the disconnect between site records and commercial reporting. The best allocation system is the one your foremen actually use consistently, whether that's paper or digital. But digital systems make the commercial team's life considerably easier when it's time to build a claim.

How detailed should a daily allocation sheet be?

Detailed enough that someone who wasn't on site could understand what each resource did, for how long, and against which activity. Every entry should have an activity reference from the programme or bill of quantities. Standing time should note the reason and duration. Plant should distinguish between working and non-productive hours. "8 labourers, 10 hours" isn't enough. "4 steel fixers, 8 hours, Activity 4.3.2 (pile caps); 4 labourers, 8 hours, Activity 5.1.1 (concrete blinding); 2 hours overtime authorised for pour completion" is what you're aiming for.

How long should you keep daily allocation sheets?

Under NEC4, you should retain all project records for the duration of the defects liability period at minimum, and typically for 6 to 12 years depending on whether the contract is executed as a deed (12 years) or under hand (6 years). For practical guidance on record retention, see our guide on how long to keep site records.

Site records, assured

Stop Losing Revenue to Incomplete Site Records

On a typical NEC4 project, poor diary records mean 40% of legitimate change goes unrecovered. Gather's QS AI Agent reviews every diary entry against clause 60.1 categories, flagging compensation events before the eight-week clock runs out.

40% more compensation events identified vs manual review