The NEC4 eight week time bar, and how to calculate it

Under unamended NEC4 ECC clause 61.3, the Contractor generally has eight weeks from awareness of an event to notify it. The exception for events the Project Manager should notify under clause 61.1 must be considered before calculating a deadline.

A date calculation is only useful once the awareness date, notification responsibility and applicable contract wording have been checked.

For an indicative calendar-date calculation, eight weeks is 56 calendar days, including weekends. Record the evidence for the awareness date and check the contract’s communication requirements, amendments and any applicable date-calculation rules. Do not assume a weekend moves the deadline to Monday. Notify promptly rather than using the last day as a target.

Check the notification rules

Read NEC’s explanation of time-barred compensation events alongside GMH’s webinar on notifying compensation events and instructing quotations. Check the applicable contract before relying on a calculated date.

Check the tools available on QS Tools

Visit QS Tools and check the available calculator’s assumptions and instructions before using an output in a contract review.

Visit QS Tools →

Gather is a construction Record Management System that helps teams organise site evidence for commercial review. To see the recording workflow, book a demo.