CPI measures cost efficiency. SPI measures schedule efficiency. Two ratios, two questions answered. The formulas take 30 seconds to learn. Knowing what to do when CPI drops to 0.85 on a £60M infrastructure package - that's the part that actually matters.
If you need a refresher on the three base inputs (PV, EV, and AC), the earned value formulas page covers those first.
What Are CPI and SPI?
Cost Performance Index (CPI) tells you how much value you're getting for every pound spent. A CPI of 1.0 means you're spending exactly what you planned. Above 1.0, you're under budget. Below 1.0, you're burning cash faster than you're delivering work.
Schedule Performance Index (SPI) tells you how fast work is progressing against the baseline programme. Above 1.0, you're ahead. Below 1.0, you're behind. Simple as that.
On a £40M rail electrification package at the time midpoint, imagine you've earned £18M of value but spent £19.6M. That's a CPI of 0.92 - and a £1.6M cost overrun already baked in, with half the project still to go. That's not a rounding error. That's a conversation with the project director, and probably a difficult one.
The CPI Formula
CPI = EV ÷ AC
Where EV is the budgeted cost of work actually completed, and AC is what you've actually spent to complete that work.
CPI Interpretation Table
| CPI Value | What It Means | Action Required |
|---|---|---|
| CPI > 1.15 | Significantly under budget | Check EV measurement - are you overclaiming progress? Or have you found genuine efficiencies? |
| CPI 1.01 to 1.15 | Under budget | Healthy. Monitor for sustainability. |
| CPI 1.00 | Exactly on budget | Rare in practice. Enjoy it. |
| CPI 0.90 to 0.99 | Slightly over budget | Investigate root cause. Recoverable if caught early. |
| CPI 0.80 to 0.89 | Over budget | Recovery plan needed. Calculate your Estimate at Completion. |
| CPI < 0.80 | Severely over budget | Escalate immediately. On a £30M project, this means overspending by more than £6M against earned progress. |
CPI trend: A persistently low cumulative CPI is a warning for final cost, but no completion percentage or recovery threshold guarantees the outturn. Compare the trend with work-package causes and a bottom-up forecast. If CPI is 0.85 at month 6, set out specific recovery actions and test their effect on remaining cost.
The SPI Formula
SPI = EV ÷ PV
Where EV is the budgeted cost of work completed, and PV is the budgeted cost of work scheduled to be completed by now.
SPI Interpretation Table
| SPI Value | What It Means | Action Required |
|---|---|---|
| SPI > 1.15 | Well ahead of schedule | Verify the baseline is realistic. Ahead of schedule is great - unless the baseline was sandbagged. |
| SPI 1.01 to 1.15 | Ahead of schedule | Strong position. Check early works aren't masking delays in later packages. |
| SPI 1.00 | On programme | Continue monitoring. |
| SPI 0.90 to 0.99 | Slightly behind | Recoverable. Check which activities are slipping and whether they're on the critical path. |
| SPI 0.80 to 0.89 | Behind schedule | Acceleration may be needed. Calculate recovery cost vs liquidated damages exposure. |
| SPI < 0.80 | Severely behind | Programme recovery workshop required. This typically needs re-sequencing, extra resources, or both. |
.webp)




