Earned Value (EV), also called Budgeted Cost of Work Performed (BCWP), is the metric that makes earned value management different from simple cost tracking. It measures what the completed work is worth according to the original budget. Not what you spent. Not what you billed. What the work is actually worth against the plan.
On a £12M project where you've completed 30% of the works, EV is £3.6M, regardless of whether you spent £3.6M, £4.2M, or £2.9M to get there. That independence from actual spend is what gives EV its diagnostic power. Compare EV against AC and you know if you're over or under budget. Compare EV against PV and you know if you're ahead or behind programme.
EV is part of the earned value definitions glossary. For the full formula reference, see the earned value formulas page.
The Formula
EV = BAC x % CompleteWhere:
- BAC = total approved project budget
- % Complete = physical percentage of work completed
The formula is simple. Measuring % Complete honestly is the hard part.
How EV Translates Physical Progress to Budget Value
The magic of earned value is the translation step. A site engineer sees "600 of 2,000 linear metres of drainage installed." A QS needs that converted into money. EV does the conversion using the original budget rates, not what the work actually cost.
FROM PHYSICAL PROGRESS TO EARNED VALUE ========================================== Physical Progress Measurement ┌─────────────────────────────────────┐ │ Activity: Main drainage run │ │ Total scope: 2,000 lin.m │ │ Installed to date: 600 lin.m │ │ % Complete: 600/2000 = 30% │ └──────────────────┬──────────────────┘ │ ▼ Budget Lookup (from priced activity schedule) ┌─────────────────────────────────────┐ │ BAC for drainage: £840,000 │ │ (2,000 lin.m @ £420/m) │ └──────────────────┬──────────────────┘ │ ▼ Earned Value Calculation ┌─────────────────────────────────────┐ │ EV = BAC x % Complete │ │ EV = £840,000 x 30% │ │ EV = £252,000 │ └──────────────────┬──────────────────┘ │ ▼ Comparison Against Actual Cost ┌─────────────────────────────────────┐ │ AC (actual spend to date): £289,000│ │ │ │ CV = EV - AC │ │ CV = £252,000 - £289,000 │ │ CV = -£37,000 (over budget) │ │ │ │ CPI = EV / AC │ │ CPI = 252,000 / 289,000 │ │ CPI = 0.87 (87p of value per £1) │ └─────────────────────────────────────┘ The drainage is 30% complete but costing 13% more than budgeted. Without EV, you'd just see "spent £289K" with no context.
Notice what EV does here. The actual cost is £289K. Is that good or bad? Without EV, you can't tell. Maybe the drainage should have cost £350K by now (good news). Maybe it should have cost £200K (disaster). EV gives you the benchmark: the work completed is worth £252K at budget rates, and you've spent £289K. That's a £37K overrun on one package. Scale that across a whole project and you start to see why EV matters.
Why Measuring Progress Is the Hard Part
I've seen project teams report 90% complete for months on end because nobody wants to admit the last 10% is where all the risk lives. On one £8M water treatment package, the reported EV was £7.2M for three consecutive months. The actual progress? Stuck at roughly 85%.
The problem isn't dishonesty. It's human psychology. Progress feels linear when it isn't. The first 80% of a structural concrete package might take 60% of the time. The last 20%, with finishing, snagging, and quality sign-offs, takes the other 40%. If your percent complete method doesn't account for this, your EV is systematically overstated in the second half of the project.
Methods for Measuring % Complete
There's no single right method. The best earned value technique depends on the work package:
| Method | Best For | Strength | Weakness |
|---|---|---|---|
| Physical units (quantities installed / total quantities) | Repetitive work, piling, drainage, cabling | Objective, auditable | Doesn't capture rework or quality issues |
| Weighted milestones | Structured packages with clear deliverables | Removes subjectivity | Requires upfront effort to define milestones and weights |
| 0/100 | Short-duration activities (< 2 periods) | Dead simple, no gaming possible | Understates progress until completion |
| 50/50 | Activities spanning 2-3 periods | Simple compromise | Overstates progress when started, understates when nearly done |
| % Complete (subjective) | Complex work with no easy physical measure | Flexible | Easily gamed, the 90% syndrome |
| Level of Effort (LOE) | Time-based overhead (site management, supervision) | Automatic, burns with time | Doesn't measure real output |
On most UK construction projects, I'd recommend physical units for anything you can count, weighted milestones for design and commissioning packages, and 0/100 for short activities. Reserve subjective % complete for the genuinely ambiguous packages and put guardrails on it, monthly sign-off by someone who's actually been on site.
Worked Example: £12M Social Housing Development
Worked ExampleScenario: You're the QS on a £12M social housing development in Birmingham under NEC4 Option A. The project is building 80 units across 4 blocks. You're at the end of month 6 of a 16-month programme. Time to calculate EV.
Step 1: Measure physical progress by package
| Package | BAC | Measurement Method | Progress | EV |
|---|---|---|---|---|
| Substructure | £1,800,000 | Physical units (foundations complete) | 80/80 = 100% | £1,800,000 |
| Superstructure | £4,200,000 | Physical units (frames erected) | 52/80 = 65% | £2,730,000 |
| Roofing | £960,000 | Physical units (roofs complete) | 20/80 = 25% | £240,000 |
| M&E first fix | £1,440,000 | Weighted milestones | 4 of 12 milestones (weighted 30%) | £432,000 |
| External works | £1,200,000 | 0/100 (not started) | 0% | £0 |
| Preliminaries | £1,680,000 | LOE (time-based) | 6/16 months = 37.5% | £630,000 |
| Contingency/risk | £720,000 | N/A (held in reserve) | 0% | £0 |
| Total | £12,000,000 | £5,832,000 |
Step 2: Compare against plan and spend
- PV at month 6 (from cost-loaded programme): £5,400,000
- EV: £5,832,000
- AC (actual Defined Cost from accounts): £6,150,000
Step 3: Derive performance metrics
- SV = EV - PV = £5,832,000 - £5,400,000 = +£432,000 (ahead of programme)
- CV = EV - AC = £5,832,000 - £6,150,000 = -£318,000 (over budget)
- SPI = EV / PV = 5,832 / 5,400 = 1.08 (8% ahead)
- CPI = EV / AC = 5,832 / 6,150 = 0.95 (5% cost overrun)
- EAC = BAC / CPI = 12,000,000 / 0.95 = £12,631,579
Translation for the project director: "We're a month ahead on programme but running a £318K cost overrun. If efficiency doesn't improve, we'll finish £632K over budget at £12.63M. The overrun is concentrated in superstructure, actual frame erection costs are running 8% above the priced rates, likely due to the crane hire rate increase in April."
That's what EV gives you. One number that connects physical progress to financial performance and lets you forecast where you'll end up.
EV on NEC4 Contracts
On NEC4, the terminology maps like this:
| EVM Term | NEC4 Equivalent |
|---|---|
| BAC | Target total of the Prices (Option C) or Activity Schedule total (Option A) |
| EV | Budgeted Defined Cost of work performed |
| AC | Defined Cost (actual) |
| PV | Budgeted Defined Cost from Accepted Programme |
The critical thing on NEC4 is that BAC changes when compensation events are implemented. If three CEs totalling £800K are implemented, your BAC moves from £12M to £12.8M. Forget to update it and every EV calculation downstream is wrong. I've seen teams running with stale BACs for months, producing beautifully formatted EVM reports full of meaningless numbers.
Common Mistakes
- The 90% syndrome: Reporting 90% complete for months because the last 10% involves testing, commissioning, and snagging that nobody wants to confront. On one project, "90% complete" lasted 4 months. If your EV has been flat for two reporting periods, something's wrong with the measurement.
- Mixing up EV and revenue: EV is not your application for payment. It's not your certified amount. It's the budgeted value of completed work. On an NEC4 Option C contract, your payment application is based on Defined Cost plus Fee. Your EV is based on progress against the target. Different numbers for different purposes.
- Not updating BAC after compensation events: Every CE implementation changes the target. If your EV formula still uses the original BAC, your CPI is artificially depressed because you're measuring new scope against the old budget. Update BAC monthly as CEs are implemented.
- Using one measurement method for everything: Defaulting to subjective % complete across all packages because it's easy. It is easy. It's also unreliable. Match the earned value technique to the work package type. The 20 minutes spent setting up proper measurement methods at the start saves months of arguing about what "65% complete" actually means.
How Gather helps. Gather's AI reads your site diaries daily and maps progress against your cost-loaded programme, giving you accurate earned value data without manual spreadsheet updates. Book a demo to see it working on a live NEC4 project.
Frequently Asked Questions
What's the difference between EV and actual cost?
EV measures what the work is worth at budget rates. AC measures what you actually spent. If they're equal, you're on budget. If EV < AC, you're overspending, each pound of budget value is costing more than a pound to deliver. The gap between them is your cost variance, and it's one of the most important numbers in project controls.
Can EV go down?
Not in standard EVM. Earned value is cumulative, once work is genuinely complete, the value is earned. But in practice, if you discover that work previously reported as complete actually needs rework (failed quality inspection, design change requiring strip-out), you should adjust the % complete downward in the next reporting period. This effectively reduces the period-on-period EV increment, though cumulative EV might appear to plateau or even dip slightly. Some teams handle this through negative EV adjustments in a separate rework column.
How is EV different from planned value?
PV is what you planned to complete by now. EV is what you actually completed. Both are measured in budget terms (not actual cost). If EV > PV, you're ahead of programme. If EV < PV, you're behind. The comparison between EV and PV gives you schedule performance; the comparison between EV and AC gives you cost performance. EV is the bridge between time and money.
Why is it called BCWP?
BCWP stands for Budgeted Cost of Work Performed, the original US Department of Defense terminology from the 1960s. "Budgeted Cost" means at budget rates, not actual rates. "Work Performed" means actually completed, not just scheduled. The term EV replaced BCWP in the late 1990s to simplify the language, but you'll still see BCWP in older textbooks and on projects influenced by US defence standards. They mean exactly the same thing.
.webp)




