Earned Value

Schedule Variance Percentage (SV%) in EVM Explained

Schedule Variance Percentage expresses schedule variance as a proportion of planned value.

Will Doyle

Will Doyle

August 27, 2026 · 5 min read

{

Schedule Variance Percentage (SV%) normalises Schedule Variance so you can compare programme performance across projects of different sizes. Raw SV is measured in pounds, which makes cross-project comparison meaningless. A -£500K SV on a £5M project is a crisis. The same -£500K on a £50M project is a rounding error. SV% strips out the scale and tells you how far behind (or ahead) you are as a percentage of the plan.

SV% = (SV / PV) x 100

Or equivalently: SV% = ((EV - PV) / PV) x 100

This term is part of the earned value definitions glossary. For the raw pound-value metric, see Schedule Variance (SV).

The Formula

FormulaSV% = SV / PV x 100

Where:

SV% RangeStatusTypical Response
> +10%Well aheadVerify it's genuine progress, not front-loading
+5% to +10%AheadMonitor. Ensure quality isn't being sacrificed for speed
-5% to +5%On trackNormal variance band on most construction projects
-10% to -5%SlippingInvestigate root cause. Yellow flag
< -10%Serious delayMandatory recovery plan. Red flag

These thresholds aren't gospel. I've worked on projects where -5% was acceptable (complex M&E with long procurement lead times) and others where -3% triggered an escalation (time-critical rail possessions with fixed handback dates). Set your thresholds during baseline approval and stick to them.

Why SV% Matters: The Normalisation Problem

Here's the scenario that makes SV% essential.

 WHY RAW SV IS MISLEADING ACROSS PROJECTS ============================================= PROJECT ALPHA (£5M retail fit-out) ├── PV at month 4 = £2,000,000 ├── EV at month 4 = £1,500,000 ├── SV = -£500,000 └── SV% = -£500K / £2M = -25% ← CRISIS. Quarter of planned work not done. PROJECT BETA (£50M hospital) ├── PV at month 10 = £22,000,000 ├── EV at month 10 = £21,500,000 ├── SV = -£500,000 └── SV% = -£500K / £22M = -2.3% ← Minor blip. Easily recoverable. ───────────────────────────────────────────── SAME SV (-£500K) COMPLETELY DIFFERENT SEVERITY ───────────────────────────────────────────── Without SV%, a portfolio director looking at two SV figures of -£500K might treat both projects equally. With SV%, it's obvious: Alpha is in serious trouble, Beta is fine.

On a programme with 8 or 10 live projects, the portfolio director doesn't have time to mentally adjust every SV figure for project size. SV% does that automatically. It's the metric that belongs in the programme-level dashboard.

The Relationship Between SV%, SV, and SPI

These three metrics all measure the same thing, schedule performance, but from different angles:

 THREE WAYS TO SAY "WE'RE BEHIND SCHEDULE" ============================================= SV = EV - PV = -£1,300,000 (how much behind, in pounds) SV% = SV / PV x 100 = -15.5% (how much behind, as a proportion of plan) SPI = EV / PV = 0.845 (efficiency: £0.85 of progress per £1 planned) ───────────────────────────────────────────── MATHEMATICAL RELATIONSHIP: SV% = (SPI - 1) x 100 ───────────────────────────────────────────── So SPI = 0.845 → SV% = (0.845 - 1) x 100 = -15.5% Use SV for absolute impact ("we're £1.3M behind") Use SV% for cross-project comparison ("Project A is -15%, B is -3%") Use SPI for efficiency and forecasting ("at this rate.")

The mathematical link between SV% and SPI is straightforward: SV% = (SPI - 1) x 100. An SPI of 0.90 always gives SV% = -10%. They're two expressions of the same ratio.

Worked Example: Comparing Two Projects in a Programme

Worked Example

Scenario: A Tier 1 contractor runs two NEC4 Option C projects simultaneously. The commercial director reviews both at the monthly programme board (October 2025).

Project 1: £5M Retail Fit-out in Manchester

  • BAC = £5,000,000
  • Duration: 8 months
  • Current month: 4 of 8 (50% through programme)
  • PV = £2,000,000
  • EV = £1,500,000
  • SV = £1,500,000 - £2,000,000 = -£500,000
  • SV% = -£500,000 / £2,000,000 x 100 = -25.0%
  • SPI = 0.750

Project 2: £50M Hospital Extension in Birmingham

  • BAC = £50,000,000
  • Duration: 24 months
  • Current month: 10 of 24 (42% through programme)
  • PV = £22,000,000
  • EV = £21,500,000
  • SV = £21,500,000 - £22,000,000 = -£500,000
  • SV% = -£500,000 / £22,000,000 x 100 = -2.3%
  • SPI = 0.977

The dashboard without SV%:

ProjectSV
Retail fit-out-£500,000
Hospital extension-£500,000

Looks equal. Feels like both need the same intervention.

The dashboard with SV%:

ProjectSVSV%SPIStatus
Retail fit-out-£500,000-25.0%0.750RED. Recovery plan needed immediately
Hospital extension-£500,000-2.3%0.977GREEN. Normal variance, monitor

Now the commercial director knows exactly where to focus. The retail fit-out at -25% needs a recovery plan by Friday. The hospital extension at -2.3% just needs monitoring.

Common Mistakes

  1. Using SV instead of SV% for portfolio reporting. If you're comparing multiple projects, raw SV is misleading. A £60M project will almost always have a larger SV than a £3M project. SV% lets you compare apples to apples.
  2. Setting the same SV% threshold for all project types. A -10% threshold makes sense for a straightforward civils job. On a complex M&E-heavy project with long procurement chains, -10% might be structurally normal for the first three months while equipment is on order. Tailor thresholds to the project type.
  3. Forgetting the convergence problem. SV% inherits the same convergence-to-zero flaw as SV. As the project nears completion, both EV and PV approach BAC, so SV shrinks and SV% trends towards zero. In the last 20% of a project, SV% becomes unreliable. Use time-based metrics like SV(t) instead.
  4. Dividing by zero at the start. At month 0, PV = 0. SV% = SV / 0 is undefined. Most EVM systems handle this by returning null until the first reporting period where PV > 0. Don't manually force it to zero. That implies on-track performance when you have no data.

How Gather helps. Gather's AI reads your site diaries daily and maps progress against your cost-loaded programme, giving you accurate earned value data without manual spreadsheet updates. Book a demo to see it working on a live NEC4 project.

Frequently Asked Questions

What SV% is considered acceptable on UK construction projects?

Most Tier 1 contractors I've worked with use a traffic light system: green at -5% to +5%, amber at -10% to -5%, red below -10%. But these aren't industry standards, they're project-specific thresholds set during baseline approval. On a fast-track programme with tight possession windows, even -5% might trigger escalation. On a long-duration infrastructure scheme, -8% in the early months might be acceptable if the critical path has float.

How often should SV% be calculated?

Monthly, aligned with your earned value reporting cycle. Some projects calculate it fortnightly, particularly on shorter-duration contracts (under 6 months) where a monthly snapshot doesn't give enough granularity. Weekly is usually overkill unless you're in a recovery phase and need to track whether acceleration measures are working.

Does SV% suffer from the same convergence problem as SV?

Yes. SV% = SV / PV, and since SV converges to zero at completion, SV% does too. A project that finishes 4 months late will show SV% = 0 at completion. For the second half of any project, supplement SV% with SPI(t) or SV(t) for an honest picture of schedule performance.

}