Estimate at Completion with Earned Schedule (EACES) represents the projected total cost of the project based on earned schedule analysis. It combines the earned value analysis with schedule performance indicators to estimate the final project cost. EACES helps in assessing the overall cost performance and forecasting the total cost of the project using earned schedule metrics.
-
Make sure you never miss out! Sign up to our monthly newsletter to keep up with the biggest news stories in construction and the latest Gather updates. Full of our latest case studies, blogs and fun quizzes!
Gather needs the contact information you provide to us to contact you about our products and services. You may unsubscribe from these communications at anytime. For information on how to unsubscribe, as well as our privacy practices and commitment to protecting your privacy, check out our Privacy Policy.