Resources / Site records templates
Free templates · Site records

Construction Site Records Templates (Free Excel Downloads)

Nine Excel templates covering the daily site record: diary, allocation, timesheets, deliveries, weather and weekly reporting. Built by the quantity surveyors behind Gather. Direct download, no form to fill in.

A site record is only worth keeping if it can later be used as evidence: to support a claim, defend against one, prove progress, or account for labour and plant. A diary entry that nobody can find or reconstruct at final account is a record in name only.

The templates in this pack

Site Diary Template

The daily record template every entry in this library builds on.

Site diaryView template
Daily Report Template

A structured daily report covering labour, plant, progress and events on site.

Site diaryView template
Allocation Sheet Template

Daily labour and plant allocation against planned resource.

Site diaryView template
Allocation Tracker

Rolls daily allocation up into a project level output tracker.

Site diaryView template
Timesheet / Labour Productivity Template

Track hours worked against output to see true labour productivity by gang.

Site diaryView template
Materials Delivery Log

Record every delivery against order, with shortfalls and damage flagged as they happen.

Site diaryView template
Weather Delay Log

Record weather events against the contractual test for a compensation event or extension of time.

Site diaryView template
Weekly Report Workbook

The natural next step from the site diary template, built for weekly reporting.

Site diaryView template
Completion Checklist

A close out checklist for handover, snagging and final account preparation.

Site diaryView template

What's in each template

TemplateCore fieldsBest for
Site DiaryDate, weather, labour, plant, materials, instructions, visitorsThe daily baseline record
Daily ReportActivities, progress narrative, issues, photos referenceClient-facing daily summary
Allocation SheetTrade, gang size, hours, plant, activity codeDaily resource capture
Allocation TrackerPlanned vs actual resource by week, varianceOutput and productivity review
Timesheet / ProductivityHours by gang, output units, productivity rateLabour cost and efficiency tracking
Materials Delivery LogOrder ref, delivery date, quantity, shortfall, damageSupply chain and procurement evidence
Weather Delay LogDate, weather measured, contractual test, impactNEC4 weather compensation events, EOT claims
Weekly Report WorkbookRolls up daily diaries into a weekly summary automaticallyWeekly client and internal reporting
Completion ChecklistSnagging items, handover documents, final account itemsClose out and handover

Records are not evidence until someone can use them

A filing cabinet of completed diaries is not the same thing as a defensible commercial position. The gap between the two is retrieval: when a dispute arises or a compensation event needs substantiating, someone has to find the right entries, cross reference them against the contract, and turn a stack of forms into an argument.

Most teams find that step out on a live project, months after the events happened, when memory has faded and the person who wrote the entry has moved on. The template you keep the record in matters less than whether the record can be searched, linked to a clause, and produced on demand.

A site record is only as good as what it can prove later.

Gather turns every diary entry into a searchable, contract-linked commercial record automatically, so the evidence is ready before you need it, not scrambled together after.

See how Gather turns records into evidence A 30 minute call. No commitment. Bring one of your live diaries.
Need the commercial trackers these records feed? See Construction Commercial Management Templates. Want the full programme and cost view? See Construction Project Controls Templates. Browse the full library at Free QS templates and tools.
What should a construction site diary record every day?

Weather, labour and plant on site, materials received, progress made, instructions given, visitors, and any event that could affect cost or programme, so the record stands on its own months later.

How long should site records be kept?

For the life of the contract at minimum, and typically 6 to 12 years afterwards for limitation purposes under English law. Keep records accessible, not just archived.

Why do good site diaries still fail to support a claim?

Because the entry describes what happened but not why it matters contractually. A weather delay log that does not reference the contractual test for a compensation event is a record of the weather, not evidence of entitlement.

Stop reconstructing site records by hand

Gather reads your diaries as they come in and keeps every commercial and programme record up to date automatically.