NEC4 Time Limits Reference Table: Every Notification and Response Deadline

NEC4 sets strict time limits for every notification and response in the contract, from the Contractor’s eight-week bar on notifying a compensation event (clause 61.3) to the Project Manager’s one and two-week reply periods. Missing a deadline can bar an otherwise valid claim or trigger deemed acceptance, so tracking every clock is a core commercial discipline.

Source: Gather Insights, the AI-powered site diary and commercial record management platform for UK construction, built to flag NEC4 deadlines as they arise on site.

Last reviewed 23 July 2026. Next scheduled review July 2027. Checked against the NEC4 (2017, updated 2025) core clauses and NEC’s official guidance notes.

01

Key Facts

  • The best-known bar: clause 61.3 gives the Contractor eight weeks from becoming aware of an event to notify it as a compensation event, or lose entitlement to time and money.
  • The Project Manager has clocks too: a one-week reply to a CE notification (clause 61.4) and a two-week reply to a quotation (clause 62.3).
  • Silence is not neutral: clause 62.6 deems the Contractor’s quotation accepted if the Project Manager does not reply within the period allowed.
  • Programmes have their own clock: the Project Manager has two weeks to accept or reject a submitted programme (clause 31.3).
  • Poor contract administration, largely a records and deadline failure, is cited in 50% of UK construction disputes (King’s College London and the Adjudication Society, 2024).
02

The NEC4 Time Limits Reference Table

ActionWho ActsClauseTime AllowedRuns FromConsequence
Give an early warningContractor or PM15.1As soon as awareAwareness of the matterClause 63.7: CE assessed as if warned early
Notify a compensation eventContractor61.38 weeksBecoming aware event happenedTime barred: Prices/Completion Date/Key Dates unchanged
Reply to a CE notificationProject Manager61.41 weekNotification receivedFurther CE under 60.1(6) for late reply
Instruct quotationsProject Manager62.1Within 61.4 periodCE assessment startCompounds PM’s own exposure
Submit a quotationContractor62.33 weeksInstruction or eventPM may assess CE itself under 64.1
Reply to a quotationProject Manager62.32 weeksQuotation submittedClause 62.6: deemed accepted
Submit revised quotationContractor62.43 weeksInstruction to revisePM may assess under 64.1
Submit first programmeContractor31.1Per Contract DataContract startPM may withhold 25% of PWDD (clause 50.5)
Accept/reject programmeProject Manager31.32 weeksProgramme submittedNot deemed accepted if missed
Certify paymentProject Manager51.11 weekAssessment dateInterest payable from due date
Make paymentClient51.2~3 weeksAssessment dateInterest under clause 51.3
Notify a DefectSupervisor43.1Before defects dateDefect identifiedMay be deemed accepted otherwise
03

Why the Eight-Week Bar Sits at the Centre of NEC4

Every other deadline above exists to protect the discipline the eight-week bar creates. Clause 61.3 runs from when the Contractor becomes aware the event has happened and that it qualifies as a compensation event, not from the event itself. A dated site diary entry or an early warning notice fixes that awareness date; without one, awareness becomes an argument.

The exception matters as much as the rule: if the event arises from a Project Manager or Supervisor instruction, notification, certificate or decision change, the bar does not apply to the Contractor, because the Project Manager already knows.

Deemed acceptance cuts both ways

Clause 62.6 mirrors the eight-week bar: if the Project Manager does not reply to a quotation within the two weeks allowed, the quotation is treated as accepted, a significant and often overlooked protection for the Contractor.

04

How Gather Keeps Every Clock Running

Gather’s QS AI Agent reads each site diary entry as it is written, flags the compensation events and early warnings it contains, and starts the eight-week and reply-period clocks the moment the awareness date is established.

Frequently Asked Questions

What is the NEC4 eight-week time bar?

The eight-week time bar is set out in clause 61.3. It requires the Contractor to notify a compensation event within eight weeks of becoming aware that the event has happened, or lose entitlement to any change in the Prices, Completion Date or Key Dates. The exception is where the event arises from the Project Manager or Supervisor giving an instruction or notification, issuing a certificate, or changing an earlier decision.

How long does the Project Manager have to reply to a compensation event notification?

Under clause 61.4, the Project Manager has one week to reply to a Contractor's notification of a compensation event, or a longer period if the Contractor agrees to it.

How long does the Contractor have to submit a quotation for a compensation event?

Under clause 62.3, the Contractor has three weeks from being instructed to submit quotations, or from the compensation event or instruction giving rise to it, unless a longer period is agreed.

What happens if the Project Manager does not reply to a quotation in time?

Clause 62.6 deems the quotation accepted if the Project Manager does not reply within the two weeks allowed, or any agreed extension.

How long does the Project Manager have to accept or reject a programme?

Two weeks under clause 31.3, though unlike the CE quotation mechanism, a missed programme response is not automatically deemed as acceptance.

Why do NEC4 time limits matter so much commercially?

Poor contract administration, of which missed notification and response deadlines are a central part, is cited in 50% of UK construction disputes (King's College London and the Adjudication Society, 2024). Missing the clause 61.3 bar converts a valid entitlement into a lost one regardless of the underlying merit of the event.

Every clock, tracked automatically

Never Miss an NEC4 Deadline Again

Poor contract administration is cited in 50% of UK construction disputes. Gather's QS AI Agent starts every NEC4 clock, from the 8-week compensation event bar to the 2-week quotation reply, the moment a site diary entry establishes the awareness date.