Estimate to Complete (ETC) with EAC represents the projected cost to complete the remaining work based on the projected total cost of the project (EAC). It subtracts the actual cost (AC) incurred from the estimated cost at completion (EAC) to determine the remaining cost needed to complete the project.
Calculation: ETC = EAC - AC
Make sure you never miss out! Sign up to our monthly newsletter to keep up with the biggest news stories in construction and the latest Gather updates. Full of our latest case studies, blogs and fun quizzes!
Gather needs the contact information you provide to us to contact you about our products and services. You may unsubscribe from these communications at anytime. For information on how to unsubscribe, as well as our privacy practices and commitment to protecting your privacy, check out our Privacy Policy.